(2) The distributor-retailer is liable
to pay the public entity any additional expense the public entity incurred in
carrying out the road works because of the location of the water
infrastructure if—
(a) either—
(i) the request was not complied with
within a reasonable period before the road works were carried out; or
(ii)
information given in response to the request did not adequately define the
location; and
(b) the additional expense would not have been incurred had the
request been complied with or had the information given adequately defined the
location.
(3) However, subsection (2) does not apply if—
(a) the road works
were not provided for in a plan by the public entity given to the
distributor-retailer within a reasonable period before the road works were
carried out; and
(b) the public entity gave a public entity approval for all
water infrastructure work for the water infrastructure; and