Queensland Consolidated Acts(1) This section applies to a building development approval for building work to--
(a) demolish or remove a building or structure; or
(b) rebuild, after removal, a building or structure.
(2) The building work must substantially start within 2 months after the giving of the approval.
(3) Within 6 months after the giving of the approval--
(a) the building work must be completed; and
(b) if the building work is rebuilding, after removal, of a building or structure, either--
(i) if, under the approval or a regulation, the building work must be inspected, a final inspection showing that the building work complies with the approval or regulation is carried out; or
(ii) under chapter 5, a certificate of classification must be given for the building.
(4) The condition under subsection (3) is the demolition/removal completion condition.