BUILDING ACT 1975
TABLE OF PROVISIONS
Long Title
Contents
CHAPTER 1--PRELIMINARY
Part 1--Introduction
1. Short title
2. Act binds all persons
3. Simplified outline of main provisions of Act
Part 2--Interpretation
Division 1--Dictionary
4. Definitions
Division 2--Key definitions
5. What is building work
6. What is a building development application
7. What is building assessment work
8. Who is a building certifier
9. Private certifiers and their classes
10. What is a building certifying function
11. Who is the assessment manager for a building development application
12. What is the Building Code of Australia (or BCA)
13. What is the Queensland Development Code (or QDC)
14. When building work complies with the BCA or QDC
Division 3--Other references
15. References to changed BCA or QDC provision
16. Reference in Act to applicants, development, assessment managers, referral agencies, building work or building certifiers
17. Reference in Act to local government
18. Reference to local government includes any other assessment manager under IPA
19. Reference to a proposed building or structure
CHAPTER 2--WHEN BUILDING WORK IS ASSESSABLE, SELF-ASSESSABLE OR EXEMPT DEVELOPMENT
20. Building work that is assessable development for IPA
21. Building work that is self-assessable for IPA
22. Building work that is exempt development for IPA
CHAPTER 3--ADDITIONAL REQUIREMENTS FOR BUILDING DEVELOPMENT APPLICATIONS
Part 1--Requirements for supporting documents
23. Operation of pt 1
24. Required information for supporting documents
25. General requirements for supporting documents
26. Requirements if alternative solution used
Part 2--Other requirements
27. Application for building work for budget accommodation building
28. Application to build swimming pool on residential land must include fencing
29. Application must include required site works
CHAPTER 4--ASSESSMENT OF BUILDING DEVELOPMENT APPLICATIONS AND CARRYING OUT SELF-ASSESSABLE BUILDING WORK
Part 1--Laws and other documents under which building work must be assessed
Division 1--General provisions about the laws and documents for the assessment
30. Relevant laws and other documents for assessment of building work
31. Building assessment provisions form a code for IDAS
32. Local laws, planning schemes and local government resolutions that may form part of the building assessment provisions
33. Alternative planning scheme provisions to QDC boundary clearance and site cover provisions for particular buildings
34. Relationship between IDAS and other building assessment provisions
35. Relationship between the BCA and the QDC
36. When building assessment provisions must be applied
37. Provision for changes to building assessment provisions
Division 2--Variation of how particular building assessment provisions apply
38. Applying to vary how particular building assessment provision applies
39. Applying for fast-track decision
40. Effect of variation application on IDAS process
41. Deciding variation application
42. Criteria for decision
43. Notice of decision
44. Effect of variation
Part 2--Persons responsible for assessing building development applications
Division 1--Who carries out building assessment work
45. Generally a building certifier must assess
46. Concurrence agencies may carry out building assessment work within their jurisdiction
Division 2--Functions of private certifiers
47. Operation of div 2
48. Functions of private certifier (class A)
49. Functions of private certifier (class B)
50. Restrictions on building certifying functions that a private certifier (class B) can perform
Division 3--Functions of local government
51. Function to act on building development application or development approval unless private certifier (class A) engaged
52. Restriction on local government issuing building development approval
53. Local government may rely on particular compliance certificates and other documents
54. Local government may rely on documents private certifier gives it for inspection or purchase
Division 4--Power of particular replacement assessment managers to decide status under IDAS
55. Power to decide what stage of IDAS application is to resume or start
Part 3--Discretionary matters in the assessment of building development applications
56. Building certifier's discretion—BCA
57. Building certifier's or concurrence agency's discretion—QDC
58. Survey certificate
59. Discretion for building development applications for particular budget accommodation buildings
60. Building certifier may rely on particular compliance certificates and other documents
61. Alterations to safe existing work may be approved on basis of earlier building assessment provisions
Part 4--Requirements for and restrictions on assessing or approving building development applications
62. Requirement to consider any advice agency response
63. Restriction on granting building development application for budget accommodation building
64. Required report before assessing application for temporary building or structure with special fire service
65. Land subject to registered easement or statutory covenant
66. Special structures
67. Temporary building or structures
68. Particular alterations not permissible
68A. Statement of reasons for approving alternative solution
Part 5--Conditions of building development approvals
Division 1--Conditions taken to be imposed
69. Operation of div 1
70. Engineering drawings
71. When demolition, removal and rebuilding must start and be completed
72. Building work in erosion prone area
73. Obligation to make current drawing available for inspection
74. Inspection and testing of special fire service installation
75. Earthworks and retaining walls
76. Drainage of buildings or land
77. Building work over existing sanitary drainage
Division 2--Conditions that may be imposed
78. Survey certificate
79. Hazardous buildings
80. Alterations to unsafe existing work
81. Building development approval for particular alterations may require existing building or structure to comply with building assessment provisions
Part 6--Regulation of building assessment work and the issuing of building development approvals by private certifiers
82. Application of pt 6
83. General restrictions on granting building development approval
84. Approval must not be inconsistent with particular earlier approvals or self-assessable development
85. Additional requirement for decision notice
86. Requirements on approval of application
87. Local government acknowledgement
88. When applicant is to be given the approval documents
Part 7--Provisions about lapsing of building development approvals and related matters
Division 1--Building work for demolition or removal
89. Application of div 1
90. Relevant period under IPA, s 3.5.21 for development approval
91. Lapsing of building development approval
92. Local government may complete particular work if condition not complied with
93. Releasing security
Division 2--Other building work
94. Application of div 2
95. Reminder notice requirement for lapsing
96. Extension of lapsing time because of application to extend relevant period under IPA, s 3.5.21
97. Restriction on private certifier (class A) extending relevant period under IPA, s 3.5.21 more than once
CHAPTER 5--INSPECTIONS, BUILDING CLASSIFICATION AND THE USE OF BUILDINGS
Part 1--Giving of inspection documentation for single detached class 1a buildings and class 10 buildings or structures
98. Application of pt 1
99. Obligation to give owner inspection documentation on final inspection
Part 2--Certificates of classification for other buildings
Division 1--Preliminary
100. Application of pt 2
101. Meaning of substantially completed
Division 2--Giving of certificate
102. Obligation to give certificate of classification on inspection after particular events
103. Certificate requirements
104. Interim certificate if building is remote
105. Certificates for a building occupied in stages
Division 3--Miscellaneous provisions about certificates of classification
106. Term of certificate of classification
107. Building certifier's obligation to give referral agency certificate and other documents
108. Additional obligations if certificate of classification given by private certifier (class A)
108A. Owner's obligations about access to certificate of classification
Part 3--Changes to BCA classification
109. What is a BCA classification change to a building
110. Restriction on making BCA classification change
111. Provision for applying to local government to obtain approval for BCA classification change
112. Concessional approval for particular existing buildings
113. Obligation of building certifier approving BCA classification change to give new certificate of classification
Part 4--Restrictions on the use of buildings
114. No occupation or use of particular buildings without certificate of classification
114A. Owner's obligation to comply with certificate of classification
115. Occupation and use of building must comply with relevant BCA and QDC provisions
116. Exception for use of government buildings for emergency
117. Enforcement action required
118. Restriction on use of buildings built on or after 1 April 1976
119. Further restriction on occupation of building for residential purposes
Part 5--Miscellaneous provisions
120. BCA classification as special structure
121. Doubtful BCA classifications
122. Building certifier's obligation to give owner inspection documentation if building development approval lapses
123. Certificate of classification for particular buildings built before 30 April 1998
124. Building certifier's obligation to give information notice about particular decisions
CHAPTER 6--PROVISIONS ABOUT PRIVATE CERTIFIERS AND OTHER BUILDING CERTIFIERS
Part 1--General provisions about building certifiers
Division 1--Regulation of the performance of building certifying functions
125. Person must not perform building certifying functions without licence
126. Building certifier performing building certifying function must be appropriately licensed
127. Building certifier's duty to act in public interest in performing building certifying function
128. Building certifier must not perform building certifying function if there is a conflict of interest
Division 2--Code of conduct
129. Code of conduct
130. Tabling and inspection of amendment or replacement not part of or attached to regulation
131. Access to code of conduct
Division 3--Miscellaneous provisions
132. Effect of building certifier not complying with Act if no penalty provided
133. Additional functions of BSA for building certification
Part 2--Private certifiers
Division 1--Regulation of private certifying functions
134. Restriction on performing functions of private certifier (class A)
135. Restriction on private certifier performing functions for building development applications
136. Offence for private certifier not to act in public interest in performing private certifying function
137. Private certifier must not perform private certifying function if there is a conflict of interest
Division 2--Engagement of private certifiers
138. Power to contract to perform private certifying functions
139. General restrictions on private certifier entering into engagement
140. Restriction on engagement of private certifier (class B)
141. Requirements for engagement of private certifier
142. Engagement of private certifier (class A) taken to include inspection and certification
143. Notice of engagement to local government
144. Restriction on discontinuing engagement
145. Effect of transfer of functions for building development approval to local government or replacement private certifier
146. Agreed fee recoverable despite valid refusal of particular actions
Division 3--Record-keeping and related requirements
147. Building development applications and approval documents
148. Obligation to give inspection documentation to owner of building
149. Obligation to give inspection documentation and any reminder notice to local government
150. Obligation to keep inspection documentation
Part 3--Licensing of building certifiers
Division 1--Licence levels and their roles
151. Levels
152. Role of building surveyor
153. Role of assistant building surveyor
154. Role of building surveying technician
Division 2--Applying for and obtaining license
155. Who may apply
156. Requirements for licence application
157. Decision on licence application
158. Steps after making decision
159. Duration of licence
Division 3--Private certification endorsements
160. Endorsements
161. Who may apply for endorsement
162. Requirements for endorsement application
163. Restrictions on making endorsement
164. Notice of refusal
Division 4--Renewals
165. Notice of expiry of licence
166. Automatic expiry on failure to apply for renewal
167. Applying for renewal
168. Existing licence taken to be in force while application is being considered
169. Decision on renewal application
170. Steps after making decision
Division 5--Cancellation and suspension of, and other changes to, licences and cancellation of endorsements
Subdivision 1--BSA's powers
171. Power to amend, cancel or suspend licence
172. Power to change licence level
173. Cancellation of endorsement of licence to act as private certifier
174. Notice of particular events to interstate licensing authorities and other entities
Subdivision 2--Show cause notice procedure
175. Show cause notice
176. Submissions about show cause notice
177. Decision on proposed action
178. Notice and taking effect of decision
Division 6--General provisions about licences
179. Register of building certifiers
180. Access to register
181. Surrendering licence
182. Obtaining replacement licence
183. Obligation of building certifier to give notice of change in particular circumstances
Division 7--Miscellaneous provisions
184. Accreditation standards bodies
185. Function of accreditation standards body
186. Criteria for deciding suitability of applicants and licensees
187. BSA may seek information from applicants about suitability
188. Refund of particular licence fees accompanying applications
189. Appeals to Commercial and Consumer Tribunal about decisions under pt 3
Part 4--Complaints, investigations and disciplinary proceedings relating to building certifiers
Division 1--Complaints
190. Making a complaint against a building certifier
191. Building certifier must be advised of complaint
192. BSA may recommend mediation to resolve complaint
193. Mediation process
194. Investigation of complaint
Division 2--Investigations
195. BSA may require documents to be produced
196. Issue of identity card to auditor
197. Production or display of identity card
198. Inspection of documents
199. Power to enter and inspect building site relating to complaint or audit
200. Procedure before entry
201. Cooperating with investigation or audit
202. False or misleading statements
203. False or misleading documents
204. Decision after investigation or audit completed
205. Review of BSA's decision
Division 3--Show cause notice for disciplinary proceedings
206. Show cause notice
207. Representations and decision
Division 4--Disciplinary proceedings
208. Commercial and Consumer Tribunal may conduct disciplinary proceeding
209. Application of Tribunal Act to disciplinary proceeding
210. Notification of disciplinary proceeding
211. Orders relating to current building certifier
212. Orders relating to former building certifier
213. Consequences of failure to comply with Commercial and Consumer Tribunal's orders and directions
214. Recording details of orders
CHAPTER 7--FIRE SAFETY FOR BUDGET ACCOMMODATION BUILDINGS
Part 1--Interpretation
215. Definitions for ch 7
216. Meaning of budget accommodation building
Part 2--Fire safety standard
217. Fire safety standard
218. Guidelines for fire safety standard
Part 3--Budget accommodation buildings built, approved or applied for, before 1 January 1992
219. Application of pt 3
220. Owner must ensure building conforms with fire safety standard
221. Approval of longer period for conformity with fire safety standard
222. Advice as to conformity with fire safety standard
223. Stay of operation of local government decision
224. Local government decisions
Part 4--All budget accommodation buildings
225. Application of pt 4
226. Obligation about fire safety management plan
227. Accessing fire safety management plan
228. Random inspection of buildings for which development approval is given
Part 5--Miscellaneous
229. Obligations of entities about guidelines for fire safety standard and fire safety management plans
230. Local government's fire safety record-keeping obligations
231. Owner's fire safety record-keeping obligation
CHAPTER 8--SWIMMING POOL FENCING
232. Definitions for ch 8
233. Meaning of fencing standards
234. Meaning of pool owner
235. Outdoor swimming pool must be fenced
236. Resuscitation sign for outdoor swimming pool
237. Replacing fencing
238. Warning sign required before constructing outdoor swimming pool
239. Constructing outdoor swimming pool
240. Application for exemption from fencing
241. Steps to be taken after application decided
242. Revocation of exemption
243. Register of exemptions
244. Advice as to compliance
245. Access to outdoor swimming pools must be kept secure
246. Apportionment of cost of constructing dividing fence
CHAPTER 9--SHOW CAUSE AND ENFORCEMENT NOTICES
247. Show cause notices
248. Enforcement notices
249. Specific requirements of enforcement notices
250. Appeals against enforcement notices
251. Register of notices given
252. Action local government may take if enforcement notice not complied with
253. Removal of persons in buildings to be demolished
CHAPTER 10--GENERAL PROVISIONS
254. Approved forms
255. Information to be supplied by the State
256. Prosecution of offences
257. Liability for corporation's default
258. Guidelines
259. Access to guidelines
260. Evidentiary aids
261. Regulation-making power
CHAPTER 11--SAVINGS AND TRANSITIONAL PROVISIONS
Part 1--Transitional provision for Local Government Act 1993
262. Swimming pool fencing compliance—hardship
Part 2--Transitional provisions for Building and Integrated Planning Amendment Act 1998
263. References to Standard Building Law etc.
264. Existing referees
265. Existing registrar
266. Lawfully constructed buildings and structures protected
Part 3--Transitional provisions for Building Amendment Act 2003
267. Definitions for pt 3
268. Existing exemption from fencing swimming pool
269. Undecided application for exemption from fencing swimming pool
270. When resuscitation sign for outdoor swimming pool not required
271. Revocation of decisions or previous variations
Part 4--Transitional provisions for Plumbing and Drainage Act 2002
272. Definitions for pt 4
273. Swimming pool fences for existing tourist resort complexes exempted
274. Unsatisfactory conduct and professional misconduct
275. Appeals to chief executive against accrediting body's decision
276. Appeal to the court against chief executive's decision
277. Orders relating to building certifiers
Part 5--Transitional provisions for Building and Other Legislation Amendment Act 2006
278. Undecided building development applications
279. Exclusion of reminder notice requirement for existing building development approvals
280. Consequential amendments to the QDC
281. Consequential amendments to code of conduct
283. Existing rainwater tank provisions in planning schemes
Part 6--Transitional provision for Building and Other Legislation Amendment Act 2008
284. Transitional provision for s 108A
SCHEDULE 1 THE QDC ON 26 FEBRUARY 2008
SCHEDULE 2 DICTIONARY
Endnotes
[Index]
[Search]
[Search this Act]
[Notes]
[Noteup]
[Download]
[Help]