71 . Retention money to be held on trust
(1) Retention money
under a construction contract to which this Part applies is, by the operation
of this section, held on trust by the party to the contract who retains the
money from the retention money trust commencement date until the retention
money trust end date.
(2) Until retention
money held on trust under this Part is paid into a retention money trust
account, the trust applies to the property of the party who retains the money,
but only to the extent of the amount of the retention money.
(3) While retention
money under a construction contract is held on trust under this
Part —
(a) it
is not available for payment to a third-party creditor of any of the parties
to the contract; and
(b) it
is not liable to be attached or taken in execution for satisfying a monetary
judgment entered in favour of a third-party creditor of any of the parties to
the contract.
(4) For the purposes
of subsection (3), a third-party creditor of a party to a construction
contract is any creditor of the party, other than the other party to the
contract in connection with a liability arising under the contract.
(5) If a court
replaces a party to a construction contract as trustee of the trust created by
this section in the exercise of its jurisdiction to supervise the
administration of the trust —
(a) the
relevant retention money is then held on trust by the replacement trustee; and
(b) the
replacement trustee has the functions under this Part of that party.