Western Australian Consolidated Regulations (1) If a diving
contractor does not already have an accepted DSMS for a proposed diving
project, the contractor must give a copy of the proposed DSMS for the project
to the Safety Authority at least 60 days before the project is expected
to begin.
(2) In accepting a
DSMS, the Safety Authority may impose any condition that it considers is
necessary in the interests of safety and health.
(3) The Safety
Authority must, within 60 days after receiving the DSMS, notify the
diving contractor —
(a) that
the DSMS is either accepted or rejected; and
(b) of
each condition imposed on the acceptance, if relevant.