20 .         Updating diving project plan

        (1)         A diving contractor conducting a diving project must keep the diving project plan for the project up-to-date during the project.

        (2)         A diving contractor conducting a diving project must update the diving project plan for the project if —

            (a)         because of modification of the project, there is a significant increase in the overall level of risk, or a significant change in the type of risk, to a person taking part in a diving operation that is part of the project; or

            (b)         the operator in relation to the project proposes to undertake or permit a modification of the project that is likely to significantly affect the level of specific risks to a person taking part in a diving operation that is part of the project or significantly change the type of risk to such a person.

        (3)         If there is not an operator in relation to a diving project and the diving project plan for the project has been updated, the diving contractor must give a copy of the updated plan to the Safety Authority.