Western Australian Consolidated Regulations (1) A diving
contractor conducting a diving project must keep the diving project plan for
the project up-to-date during the project.
(2) A diving
contractor conducting a diving project must update the diving project plan for
the project if —
(a)
because of modification of the project, there is a significant increase in the
overall level of risk, or a significant change in the type of risk, to a
person taking part in a diving operation that is part of the project; or
(b) the
operator in relation to the project proposes to undertake or permit a
modification of the project that is likely to significantly affect the level
of specific risks to a person taking part in a diving operation that is part
of the project or significantly change the type of risk to such a person.
(3) If there is not an
operator in relation to a diving project and the diving project plan for the
project has been updated, the diving contractor must give a copy of the
updated plan to the Safety Authority.