PETROLEUM (SUBMERGED LANDS) (PIPELINES) REGULATIONS 2007 - REG 44

44 .         Acceptance or rejection of pipeline safety management plan

        (1)         This regulation applies if, under regulation 23, the Minister gives the Safety Authority a copy of a pipeline management plan.

        (2)         The Safety Authority must, within 21 days —

            (a)         consider the pipeline safety management plan within the pipeline management plan; and

            (b)         decide —

                  (i)         to accept the pipeline safety management plan in full; or

                  (ii)         to reject the pipeline safety management plan; or

                  (iii)         to accept the pipeline safety management plan in relation to one or more, but not all, prescribed activities to which the pipeline management plan relates and refuse to accept the rest of the pipeline safety management plan; or

                  (iv)         that it is unable to make a decision on the pipeline safety management plan;

                and

            (c)         notify the Minister, in writing, of the Safety Authority’s decision and the reasons for any refusal.

        (3)         The Safety Authority —

            (a)         may impose conditions on the acceptance of a pipeline safety management plan in full or in relation to one or more, but not all, prescribed activities to which the pipeline management plan relates; and

            (b)         must, in the notice under subregulation (2)(c), include the conditions imposed.

        (4)         If the Safety Authority is unable to make a decision on the pipeline safety management plan, the Safety Authority must include in the notice under subregulation (2)(c) —

            (a)         a proposed timetable for consideration of the pipeline safety management plan that gives the pipeline licensee a reasonable opportunity to modify or resubmit the pipeline safety management plan; and

            (b)         a description of any further information the Safety Authority may require to assist it to consider the pipeline safety management plan.