Western Australian Consolidated Regulations (1) Within
28 days after a pipeline licensee submits a pipeline management plan, the
Minister must —
(a)
accept or reject the plan under regulation 25; or
(b) give
written notice to the pipeline licensee stating that the Minister is unable to
make a decision about the plan within the period of 28 days, and setting
out a proposed timetable for consideration of the plan.
(2) A failure by the
Minister to comply with subregulation (1) in relation to a pipeline
management plan does not of itself invalidate a decision to accept or reject
the plan.
(3) This regulation
applies to a pipeline management plan resubmitted under regulation 25(3)
in the same way as it applies to the plan when first submitted.