Western Australian Consolidated Regulations (1) Within
30 days after a titleholder gives a well operations management plan to
the Minister, the Minister must —
(a)
accept the well operations management plan, or one or more parts of the well
operations management plan;
(b)
reject the well operations management plan; or
(c)
notify the titleholder, in writing, that the Minister is unable to make a
decision without further assessment of the well operations management plan.
(2) If the Minister is
unable to make a decision, the Minister must —
(a)
notify the titleholder, in writing, that the Minister is unable to make a
decision without further assessment of the well operations management plan;
and
(b)
include in the notification —
(i)
a proposed timetable for assessment of the well
operations management plan that gives the titleholder a reasonable opportunity
to modify and resubmit the well operations management plan; and
(ii)
a description of any further information the Minister may
require to be able to assess the well operations management plan.
(3) If a well
operations management plan is resubmitted under subregulation (2)(b)(i),
or further information is provided under subregulation (2)(b)(ii), the
Minister must, as soon as practicable, further assess the well operations
management plan and either —
(a)
accept the well operations management plan, or one or more parts of the well
operations management plan; or
(b)
reject the well operations management plan.
(4) The Minister may
accept a well operations management plan, or one or more parts of the well
operations management plan, subject to any conditions decided by the Minister.
(5) The acceptance of
one or more parts of a well operations management plan is taken to be the
rejection of any other parts of the well operations management plan that are
not accepted by the Minister.
(6) The Minister must
notify the titleholder, in writing, of the following matters as soon as
practicable after making a decision —
(a) the
terms of the decision;
(b) if
the decision is to reject, or accept one or more parts of, the well operations
management plan, the reasons for the decision;
(c) if
the decision is to accept the well operations management plan, or one or more
parts of the well operations management plan, subject to a
condition —
(i)
the terms of the condition; and
(ii)
the reason for making the acceptance subject to the
condition;
(d) the
terms of regulation 14.