Western Australian Consolidated Regulations[r. 48(4)]
|
Task 1 |
Estimated hours 2 | |||||
| |
Head of planning |
Senior Planner |
Planning Officer |
Other staff e.g. environmental health officer |
Secretary/ administrative officer | |
|
1. Preliminaries: | ||||||
|
Preliminary discussions and registration of application | | | | | | |
|
2. Decision to advertise: | ||||||
|
(a) Information and site visit | | | | | | |
|
(b) Proponent discussion | | | | | | |
|
(c) Development Control Unit (DCU) meeting | | | |
|||
|
(d) Action DCU recommendation | | | | | | |
|
(e) Assessment report and agenda preparation | | |
||||
|
3. Approval to advertise: | ||||||
|
(a) Action local government recommendation | | | |
|||
|
(b) Advertising, notifications, referrals | | | |
| ||
|
(c) Deal with enquiries | | | | | | |
|
(d) Assess submissions | | | | | | |
|
(e) Liaise with external agencies | | | | | | |
|
(f) Proponent discussion and liaison | | | | | | |
|
4. Decision to adopt: | ||||||
|
(a) Finalise report and agenda preparation | | | |
|||
|
(b) Proponent discussion | | | | | | |
|
(c) Action local government recommendation | | | |
|||
|
5. Plan adopted: | ||||||
|
(a) Refer to Commission for endorsement | | | | |
| |
|
(b) Notification and deposit of plan | | | | | | |
|
Total hours | | | | | | |
|
Hourly rate (r. 48(5)) |
$ |
$ |
$ |
$ |
$ | |
|
Total hours x rate = |
$ |
$ |
$ |
$ |
$ | |
|
+ 33.3% (To recover operating overhead costs) |
$ |
$ |
$ |
$ |
$ | |
|
= Total salary costs |
$ |
$ |
$ |
$ |
$ | |
|
Total salary costs b/f |
$ | |||||
|
+ Direct costs |
$ | |||||
|
+ Special costs |
$ | |||||
|
= Estimated total fee |
$ | |||||
Notes to Form —
1. This form is based
on the Western Australian Planning Commission’s draft model text
provisions for structure plans. If the structure plan provisions in a local
planning scheme of a local government are not consistent with the draft model
text provisions, the fees should be calculated by that local government in
accordance with the structure plan provisions of the scheme.
2.
If readvertising of a proposed structure plan is required, the
hours needed to arrange the readvertising and review the submissions and the
direct costs incurred in readvertising the plan are to be included in items 3,
4 and 5.