NATIONAL THIRD PARTY ACCESS CODE FOR NATURAL GAS PIPELINE SYSTEMS - REG 8.26
NATIONAL THIRD PARTY ACCESS CODE FOR NATURAL GAS PIPELINE SYSTEMS - REG 8.26
8.26
A Service Provider may
levy a Surcharge on Users of Incremental Capacity provided the following
principles apply:
(a) the
Surcharges are designed to recover only that part of the New Facilities
Investment that satisfies the requirement in section 8.16(a)(i);
(b) the
costs that the Surcharges are designed to recover do not include any costs
that are included in the Speculative Investment Fund; and
(c) the
structure of the Surcharges reflect a fair and reasonable sharing of the total
recoverable cost between Incremental Users (and for this purpose any User who
is paying a Capital Contribution should be assumed to be paying a Surcharge).
[Section 8.26 amended: Gazette
2 May 2003 p. 1526.]