8.13
If the period between
the time the Covered Pipeline first enters service and the time the Reference
Tariff is proposed is such as reasonably to warrant adjustment to the actual
capital cost in establishing the initial Capital Base, then that cost should
be adjusted to account for New Facilities Investment or the Recoverable
Portion (whichever is relevant), Depreciation and Redundant Capital incurred
or identified during that period (as described in section 8.9).