3.33

                The Relevant Regulator must decide to approve the Final Approval Request if satisfied of all of the following and must decide not to approve the Final Approval Request if not satisfied of all of the following:

            (a)         that the successful tender was selected in accordance with the selection criteria specified in the Tender Approval Request approved by the Relevant Regulator under section 3.25;

            (b)         that the tender process was conducted in accordance with the procedures and rules specified in the Tender Approval Request approved by the Relevant Regulator under section 3.25;

            (c)         that the Reference Tariffs determined in accordance with the tender process:

                  (i)         achieve the objectives in section 8.1; and

                  (ii)         contain or reflect an allocation of costs between Services and an allocation of costs between Users which is fair and reasonable;

            (d)         that the Revisions Commencement Date in the Access Arrangement for the proposed Pipeline is not later than 15 years after the Access Arrangement for the proposed Pipeline is approved or such later date as the Relevant Regulator considers appropriate for the proposed Pipeline on the basis of the proposed tariffs (including but not limited to Reference Tariffs); and

            (e)         that the successful tenderer’s Access Arrangement for the proposed Pipeline will contain an Additional Revenue Policy that is appropriate for the proposed Pipeline on the basis of the proposed tariffs (including but not limited to Reference Tariffs).