• Specific Year
    Any

NATIONAL THIRD PARTY ACCESS CODE FOR NATURAL GAS PIPELINE SYSTEMS - REG 3.25

NATIONAL THIRD PARTY ACCESS CODE FOR NATURAL GAS PIPELINE SYSTEMS - REG 3.25

3.25

                Within 28 days of the date specified in the notice published under section 3.23(b), the Relevant Regulator must make a decision in relation to a Tender Approval Request that:

            (a)         approves the Tender Approval Request; or

            (b)         does not approve the Tender Approval Request.

                In making a decision under this section 3.25 the Relevant Regulator must consider any submissions received within the time specified in the notice published under section 3.23(b) and may (but is not obliged to) consider any submissions received after the time.