BUILDING REGULATIONS 2012 - SCHEDULE 3

BUILDING REGULATIONS 2012 - SCHEDULE 3

[r. 27]

1 .         Term used: EP

                In this Schedule —

        EP , followed by a number, means the performance requirement of that description set out in the Building Code.

Table

Column 1

System to be tested

Column 2

When test to be conducted

Fire hose reel system required under E1P1 and E1P5

On completion of the installation of the system

Fire hydrant system required under E1P3 and E1P5

On completion of the installation of the system

Automatic fire suppression system required under E1P4

On completion of the installation of the system

Fire detection, warning, control and intercom systems required under E2P1 and E2P2

On completion of the installation of the system

Air handling systems that incorporate smoke control provisions required under E2P2

On completion of the building work

Smoke/heat venting systems required under E2P2

On completion of the installation of the system

Emergency warning and intercom systems required under E4P3

On completion of the installation of the system

        [Schedule 3 amended: Gazette 24 Apr 2014 p. 1141; 26 Mar 2019 p. 946; SL 2022/162 r. 15.]