• Specific Year
    Any

BUILDING REGULATIONS 2012 - REG 54A

BUILDING REGULATIONS 2012 - REG 54A

54A .         Temporary pool barriers

        (1)         In this regulation —

        person responsible has the meaning given in section 75;

        work has the meaning given in section 75.

        (2)         A person responsible for work that requires the removal of a fence, wall, gate or other component that is part of a barrier to a private swimming pool must ensure that an alternative barrier that complies with regulation 50 is installed or provided for any period during which the fence, wall, gate or component is removed.

        [Regulation 54A inserted: Gazette 24 Apr 2014 p. 1140; amended: Gazette 15 Apr 2016 p. 1171.]