BUILDING REGULATIONS 2012 - REG 54A
BUILDING REGULATIONS 2012 - REG 54A
54A . Temporary pool barriers
(1) In this
regulation —
person responsible has the meaning given in
section 75;
work has the meaning given in section 75.
(2) A person
responsible for work that requires the removal of a fence, wall, gate or other
component that is part of a barrier to a private swimming pool must ensure
that an alternative barrier that complies with regulation 50 is installed
or provided for any period during which the fence, wall, gate or component is
removed.
[Regulation 54A inserted: Gazette 24 Apr 2014
p. 1140; amended: Gazette 15 Apr 2016 p. 1171.]