BUILDING REGULATIONS 2012 - REG 41
BUILDING REGULATIONS 2012 - REG 41
41 . Building work for which building permit not required (s. 9(b))
(1) A building permit
is not required for the following building work —
(a)
building work for a Class 10 building or incidental structure that is located,
or to be located, in a local government district specified in column 1 of the
Table in the area specified for that district in column 2 of the Table;
(b)
building work for a building or incidental structure that is not a Class 10
building or incidental structure and that is located, or to be located, in a
local government district specified in column 1 of the Table in the area (if
any) specified for that district in column 3 of the Table.
(2) In
subregulation (1)(a) and (b) —
Table means the Table in Schedule 4
clause 1.
(3) A building permit
is not required for building work of a kind described in the Table in
Schedule 4 clause 2.
(4) A builder who
constructs, erects, assembles or places a temporary office, shed or sanitary
facility in the circumstances described in item 3 in the Table in
Schedule 4 clause 2 must not, without the written approval of the
permit authority, allow the office, shed or sanitary facility to remain on the
land after the completion of the building work in connection with which it was
constructed, erected, assembled or placed.
Penalty: a fine of $5 000.