BUILDING REGULATIONS 2012 - REG 40
BUILDING REGULATIONS 2012 - REG 40
40 . Extension of period of duration of time limited occupancy permit or building approval certificate (s. 65)
(1) In this
regulation —
application means an application made under
section 65(1);
expiry day , in relation to an occupancy permit or
a building approval certificate, means the day on which the permit or
certificate ceases to have effect.
(2) A permit authority
may, by written notice, refuse to accept an application made after the expiry
day for the occupancy permit or building approval certificate if —
(a) the
permit authority is satisfied that the delay in making the application was
unreasonable in the circumstances; or
(b) the
application is made more than 30 days after the expiry date for the
permit.
(3) If an application
is made before the expiry day for an occupancy permit or a building approval
certificate and has not been determined by the expiry day, the permit or
certificate continues to have effect on and from expiry day until —
(a) the
permit authority extends or refuses to extend the permit or certificate; or
(b) the
applicant withdraws the application; or
(c) a
notice of completion in respect of the building to which the permit or
certificate relates is given to the permit authority; or
(d) a
period of 30 days has elapsed since the expiry of the building permit for
the building.
(4) If an application
made after the expiry day for an occupancy permit or a building approval
certificate is accepted by the permit authority, the permit or certificate is
to be taken to have had effect on and from the day immediately following the
expiry day until —
(a) the
permit authority extends or refuses to extend the permit or certificate; or
(b) the
applicant withdraws the application; or
(c) a
notice of completion in respect of the building to which the permit or
certificate relates is given to the permit authority; or
(d) a
period of 30 days has elapsed since the expiry of the building permit for
the building.
(5) If a permit
authority refuses to extend the time during which an occupancy permit or a
building approval certificate has effect or extends the permit or certificate
for a shorter period than the period requested by the applicant, the permit
authority must —
(a)
record the grounds on which the decision is based and the reasons for the
decision; and
(b) as
soon as is practicable, but in any case not later than 5 business days
after making the decision, give to the applicant written notice of the
decision together with those grounds and reasons, and the person’s right
of review under section 121(2).