BUILDING REGULATIONS 2012 - REG 26
BUILDING REGULATIONS 2012 - REG 26
26 . Approval of new responsible person (s. 35(c))
(1) For the purposes
of section 35(c), the owner of a building or incidental structure to
which a permit applies may apply to the relevant permit authority for approval
of a new responsible person for the work to which the permit applies if the
permit does not have effect for a reason mentioned in section 35(a)
or (b).
(2) An application
must name, and be signed by, the new person who proposes to be
named —
(a) as
the builder on the building permit; or
(b) the
demolition contractor on the demolition permit.
(3) On an application
under subregulation (1), a permit authority must —
(a)
approve a new person to be named as the builder on the building permit if the
permit authority is satisfied of the matters mentioned in
section 20(1)(b)(i) to (iii) in relation to the person; or
(b)
approve a new person to be named as the demolition contractor on the
demolition permit if the permit authority is satisfied of the matters
mentioned in section 21(1)(b) in relation to the person.
(4) If a permit
authority approves a new responsible person in relation to a permit, the
permit authority must amend the details set out in the permit accordingly.
[Regulation 26 amended: Gazette
18 Dec 2012 p. 6562.]