20 . Time for deciding application for building or demolition permit (s. 23)
(1) For the purposes
of section 23(1)(a), the period for buildings of all classifications
is —
(a) if
the application relates to development as defined in the
Planning and Development Act 2005 section 4 and a planning scheme or
interim development order that has effect under that Act provides that the
development is not to be commenced or carried out without an approval being
obtained upon the making of a development application —
(i)
25 business days, excluding any day that is after the day
on which the development application is made and before the day on which that
application is determined; or
(ii)
such longer period as is agreed in writing between the
applicant and the permit authority;
and
(b)
otherwise, 25 business days, or such longer period as is agreed in writing
between the applicant and the permit authority.
(2) For the purposes
of section 23(2)(a), the period for buildings of all classifications is
10 business days, or such longer period as is agreed in writing between the
applicant and the permit authority.
[Regulation 20 amended: Gazette 15 Jun 2012
p. 2514‑15.]