HOME BUILDING CONTRACTS ACT 1991 - SECT 5
HOME BUILDING CONTRACTS ACT 1991 - SECT 5
5 . Owner to be given copy of contract
(1) The owner must be
given a copy of the signed contract —
(a) as
soon as is reasonably practicable after a contract has been signed by both
parties; and
(b)
before the home building work is commenced.
(2) A builder who is a
party to a contract must ensure that the requirements of subsection (1) are
complied with in respect of that contract.
Penalty: $500.
(3) If —
(a)
subsection (1) is not complied with by a builder in respect of a signed
contract; and
(b) the
owner in writing requests the builder to give to the owner a copy of the
contract,
the builder must
comply with that request within 10 working days of receiving it.
Penalty: $10 000.
[Section 5 amended: No. 76 of 2000 s. 45.]