BUILDING REGULATIONS 2018 (SR NO 38 OF 2018) - REG 77 Permeability

BUILDING REGULATIONS 2018 (SR NO 38 OF 2018) - REG 77

Permeability

    (1)     If—

        (a)     an allotment is in a zone of a planning scheme specified in Schedule 6; and

        (b)     a schedule to that zone specifies that an allotment must have a minimum area of permeable surfaces—

the amount of the allotment that must have a permeable surface must not be less than the minimum area of permeability specified in that schedule.

    (2)     If subregulation (1) does not apply, and if a building is to be constructed on an allotment, at least 20% of the area of the allotment must have a permeable surface.

    (3)     The report and consent of the relevant council must be obtained to an application for a building permit in relation to a design that does not comply with this regulation.