Water Act 1989 - SECT 22R
Review process
22R. Review process
(1) In conducting a review under section 22P, the Minister must-
(a) consult with the consultative committee appointed by the Minister
under section 22Q;
(b) give notice of the review to any Authority or other person whose
interests the Minister considers are likely to be affected by the
review;
(c) publish notice of the commencement of the review in a local newspaper
circulating generally in the area to which the review relates;
(d) make any draft review available for inspection by the public for at
least 2 months after its preparation;
(e) publish a notice in a newspaper, circulating generally in the State
and a local newspaper circulating generally in the area to which the
review relates, stating where and when the draft review can be
inspected and inviting public comment by a set date;
(f) consider any comments made by the set date;
(g) consider any comments of the panel appointed under section 22S;
(h) make any appropriate changes to the draft review.
(2) The Minister must ensure that any review under section 22P-
(a) that is conducted as a result of a long-term water resources
assessment commenced under section 22K(a) is conducted in such a
manner as to be completed not more than 14 years and 6 months after
the commencement of section 14 of the Water (Resource Management) Act
2005; and
(b) that is conducted as a result of a long-term water resources
assessment commenced under section 22K(b) is conducted in such a
manner as to be completed 6 months before the end of the 15 year
period in which it commenced.
(3) Failure to comply with subsection (2) does not affect the validity of the
review or of any action the Minister takes under the review, including, but
not limited to any action under section 33AAB.