Victorian Consolidated Legislation

[Index] [Search] [Notes] [Noteup] [Download] [Help]

VICTORIAN RENEWABLE ENERGY ACT 2006

No. 72 of 2006
Version incorporating amendments as at 1 July 2009

TABLE OF PROVISIONS

           Section Page

   PART 1-PRELIMINARY

   1.      Purpose
   2.      Commencement
   3.      Definitions
   4.      Objects
   5.      Approved interstate renewable energy regime
   6.      Crown to be bound
   7.      Extra-territorial operation

   PART 2-RENEWABLE ENERGY CERTIFICATES

           Division 1-Registration of persons

   8.      Who may apply to be registered?
   9.      ESC may require further information and undertakings from applicants
   10.     ESC to approve or refuse application
   11.     ESC to allocate registration numbers

           Division 2-Provisional accreditation of power stations

   12.     Application for provisional accreditation of a relevant power station
   13.     ESC may give provisional accreditation
   14.     Time limit for deciding applications

           Division 3-Accreditation of power stations

   15.     Application for accreditation
   16.     ESC may require further information and undertakings from applicants
   17.     ESC to decide certain matters
   18.     ESC to approve or refuse application
   19.     Time limit for deciding applications
   20.     Nominated person for accredited power station
   21.     ESC to allocate identification codes
   22.     What is an eligible renewable energy source?
   23.     What is not an eligible renewable energy source?
   24.     Specification of energy sources as eligible renewable
           energy sources
   25.     ESC rules may provide for or in relation to meaning of
           energy sources

           Division 4-Creation of certificates
           Subdivision 1-Electricity generation

   26.     Creating certificates for additional renewable electricity
   27.     When certificates may be created
   28.     Certificates must not be created if Commonwealth certificates already created
   29.     Electricity generation returns
           Subdivision 2-Small generation units
   30.     When a certificate may be created
   31.     How many certificates may be created
   32.     Who may create a certificate?
   33.     No other certificates to be created
   34.     Certificates must not be created if Commonwealth certificates already created
   35.     Election to not create certificates under this Subdivision
   36.     Small generation unit returns
           Subdivision 3-End of right to create certificates
   37.     No certificates can be created on or after 1 January 2031.
           Subdivision 4-Improper creation of certificates
   38.     Improper creation of certificates-offences

           Division 5-Form and registration of certificates

   39.     Form and content of certificates-accredited power stations
   40.     Form and content of certificates-small generation units
   41.     Certificates must be registered

           Division 6-Transfer of certificates

   42.     Certificates may be transferred
   43.     ESC to be notified

           Division 7-Retirement of certificates

   44.     Owner may surrender certificate
   45.     Retirement of certificates

           Division 8-Suspension of registration

   46.     Suspension of registration-conviction for improper creation
           of certificates
   47.     Suspension of registration-other grounds

           Division 9-Changing the nominated person for an accredited
           power station

   48.     Changing the nominated person for an accredited power
           station

           Division 10-Varying what constitutes a power station

   49.     Varying what constitutes an accredited power station

           Division 11-Suspending the accreditation of a relevant power station

   50.     Suspending the accreditation of a relevant power station-interconnected power stations
   51.     Suspending the accreditation of a power station-other
           grounds
   52.     Suspending the accreditation of a power station-
           circumstances specified by Governor in Council

           Division 12-Varying pre-scheme capacity and scheme capacity

   53.     Varying pre-scheme capacity and scheme capacity

   PART 3-ACQUISITIONS OF ELECTRICITY

   54.     What is a standard scheme acquisition?
   55.     What is a notional scheme acquisition?
   56.     What is an excluded acquisition?
   57.     Specification of standard scheme acquisitions and notional scheme acquisitions as excluded acquisitions
   58.     Special provision for transactions involving NEMMCO
   59.     ESC rules to determine amount of electricity acquired

   PART 4-RENEWABLE ENERGY CERTIFICATE
   SHORTFALL

           Division 1-Prohibition of renewable energy certificate shortfall

   60.     Who is a relevant entity?
   61.     Prohibition of renewable energy certificate shortfall
   62.     Civil penalty for shortfall
   63.     Shortfall penalty rate
   64.     Determination of renewable energy certificate shortfall

           Division 2-Renewable power percentage

   65.     Renewable power percentage
   66.     Required GWh of electricity from eligible renewable energy sources

   PART 5-STATEMENTS AND SURRENDER OF
   CERTIFICATES

   67.     Annual energy acquisition statements
   68.     Fees for surrender of certificates
   69.     Restrictions on certificates that can be surrendered

   PART 6-CIVIL ENFORCEMENT

           Division 1-Renewable energy shortfall penalty

   70.     Shortfall statement
   71.     Application for declaration and order for payment of shortfall penalty

           Division 2-Surrender of additional certificates where
           undertaking breached

   72.     Certificate surrender notice
   73.     Application for declaration and order requiring surrender of certificates

           Division 3-Surrender of additional certificates following
           improper creation of certificates

   74.     ESC may require surrender of certificates following
           improper creation of certificates

   PART 7-REVIEW OF ESC DECISIONS

   75.     Review of decisions

   PART 8-ROLE OF ESC

   76.     Role of ESC
   77.     ESC must publish certain information
   78.     Annual report

   PART 9-REGISTERS

           Division 1-General

   79.     Registers to be maintained

           Division 2-The register of registered persons

   80.     Register of registered persons

           Division 3-The register of accredited power stations

   81.     Register of accredited power stations

           Division 4-The register of renewable energy certificates

   82.     Register of renewable energy certificates

           Division 5-The register of applications for accredited power
           stations

   83.     Contents of register of applications for accredited power
           stations

           Division 6-Form of registers

   84.     Form of registers

   PART 10-INFORMATION-GATHERING POWERS

   85.     ESC may obtain information and documents
   86.     Failure to comply with notice
   87.     Protection against self-incrimination
   88.     Copies of documents
   89.     ESC may retain documents

   PART 11-POWERS OF AUTHORISED OFFICERS

           Division 1-Appointment of authorised officers and identity cards

   90.     Appointment of authorised officers
   91.     Identity cards

           Division 2-Powers of authorised officer
           Subdivision 1-When may powers be exercised

   92.     When may powers be exercised?
           Subdivision 2-Monitoring powers
   93.     Entry to premises
   94.     Information to be provided to occupier on entry
   95.     Entry with consent
   96.     Entry with monitoring warrant
   97.     Monitoring powers of authorised officers
           Subdivision 3-Powers to ask questions and seek production of documents
   98.     Authorised officer may ask for information
   99.     Authorised officer may require information
   100.    Failure to produce documents or answer questions
   101.    Protection against self-incrimination

           Division 3-Occupiers' rights and responsibilities

   102.    Occupier may be present during execution of warrant
   103.    Occupier to provide authorised officer with assistance

           Division 4-Monitoring warrants

   104.    Monitoring warrants

   PART 12-CONFIDENTIALITY

   105.    Disclosure of information and offence
   106.    Information may be disclosed to specified persons or bodies

   PART 13-GENERAL

           Division 1-General offences

   107.    False or misleading information
   108.    Failure to provide documents
   109.    Offences by bodies corporate

           Division 2-Evidence and records

   110.    Evidence
   111.    Records to be kept by registered persons and relevant entities

           Division 3-Fees

   112.    Fees

           Division 4-ESC rules

   113.    ESC rules

           Division 5-Review of Act

   114.    Review of operation of Act

   PART 14-AMENDMENT OF ESSENTIAL SERVICES COMMISSION ACT 2001.

   115.    Functions
   116.    New section 10C inserted
           energy
   117.    Delegation
           __________________
           SCHEDULE-Undertakings to be given to the Esc

   PART 1-UNDERTAKINGS TO BE GIVEN BY REGISTERED PERSON APPLICANTS
   1. Undertakings for registered person applicants who are Commonwealth scheme participants
   2. Undertakings for registered person applicants who are not Commonwealth scheme participants

   PART 2-UNDERTAKINGS TO BE GIVEN BY ACCREDITED POWER STATION APPLICANTS
   3. Undertakings for applicants who are Commonwealth scheme participants
   4. Undertakings for applicants who are not Commonwealth
   scheme participants
   ---------------
           ENDNOTES
           1. General Information
           2. Table of Amendments
           3. Explanatory Details


[Index] [Search] [Notes] [Noteup] [Download] [Help]