PLANNING AND ENVIRONMENT ACT 1987 - SECT 81 Applications for review relating to extensions of time

PLANNING AND ENVIRONMENT ACT 1987 - SECT 81

Applications for review relating to extensions of time

    (1)     Any person affected may apply to the Tribunal for review of—

        (a)     a decision of the responsible authority refusing to extend the time within which any development or use is to be started or any development completed; or

S. 81(1)(aa) inserted by No. 48/1991 s. 61(3)(c).

        (aa)     a decision of the responsible authority refusing to extend the time within which a plan under the Subdivision Act 1988 is to be certified, in the case of a permit relating to any of the circumstances mentioned in section 6A(2) ; or

        (b)     the failure of the responsible authority to extend the time within one month after the request for extension is made.

S. 81(2) inserted by No. 81/2004 s. 28.

    (2)     An applicant for a permit may apply to the Tribunal for a review of a decision of a responsible authority under section 54A to refuse to extend the time within which information must be given by the applicant under section 54.

S. 81(3) inserted by No. 3/2013 s. 61(1).

    (3)     Despite subsection (1) and clause 62 of Schedule 1 to the Victorian Civil and Administrative Tribunal Act 1998 , an application cannot be made to the Tribunal for review of a decision referred to in subsection (1)(a) or (aa) or a failure referred to in subsection (1)(b) unless the request to the responsible authority for the extension of time was made within the time specified under section 69(1) or (1A) (as the case requires).

S. 82 (Heading) inserted by No. 3/2013 s. 68(6).