PETROLEUM ACT 1998 - SECT 133 Time limit on compensation claims
PETROLEUM ACT 1998 - SECT 133
Time limit on compensation claimsA claim for compensation for any loss or damage under section 129 by the owner or occupier of private land or under section 132 which is not the subject of an agreement between the relevant parties may be made at any time until the end of the period of 3 years—
(a) after the loss or damage occurred; or
(b) after the authority is surrendered or cancelled or expires—
whichever is the earlier.