56E. Direction to Link corporation
(1) The Link corporation may apply to the Minister for a direction under this
section if-
(a) a Utility has not completed the works required by a direction under
section 56D within the period specified in the direction; or
(b) the Link corporation believes on reasonable grounds that the works
required by a direction under section 56D will not be completed within
the period specified in the direction.
(2) On an application under this section, the Minister, after consultation
with the Utility Minister, may direct the Link corporation to carry out or
complete the works required by the relevant direction under section 56D.
(3) Without limiting subsection (2), a direction under this section may
specify a period within which the works must be performed even if this is a
different period from any period provided for in the approved Utility
agreement or determination or the relevant direction under section 56D.
(4) If the Link corporation complies under a direction under this section with
a requirement imposed on a Utility or any other person, the Utility or other
person is not required to comply with that requirement.