• Specific Year
    Any

ELECTRICITY SAFETY ACT 1998 - SECT 110 Offence to fail to submit revised electricity safety management scheme on request

ELECTRICITY SAFETY ACT 1998 - SECT 110

Offence to fail to submit revised electricity safety management scheme on request

If Energy Safe Victoria requests the revision of an electricity safety management scheme in accordance with section 109, the major electricity company must submit a revised electricity safety management scheme for a supply network to Energy Safe Victoria—

        (a)     if the major electricity company does not make a submission under that section, within the time (being not less than 60 days) specified by Energy Safe Victoria in the request; or

        (b)     if the major electricity company has made a submission under that section and Energy Safe Victoria has not withdrawn the request, within the time (being not less than 60 days) specified by Energy Safe Victoria in the decision on the submission.

Penalty:     In the case of a natural person, 80 penalty units;

In the case of a body corporate, 400 penalty units.

S. 111 substituted by No. 61/2007 s. 7.