Domestic Building Contracts Act 1995 - SECT 23

Builder must supply evidence of cost of prime cost items and provisional sums

23. Builder must supply evidence of cost of prime cost items and provisional
sums

A builder must give the building owner a copy of any invoice, receipt or other
document that shows the cost to the builder of any prime cost item, or that
relates to any provisional sum, in a domestic building contract and must do so
as soon as practicable after receiving the invoice, receipt or document.
Penalty: 20 penalty units.