DOMESTIC BUILDING CONTRACTS ACT 1995 - SECT 23 Builder must supply evidence of cost of prime cost items and provisional sums
DOMESTIC BUILDING CONTRACTS ACT 1995 - SECT 23
Builder must supply evidence of cost of prime cost items and provisional sumsA builder must give the building owner a copy of any invoice, receipt or other document that shows the cost to the builder of any prime cost item, or that relates to any provisional sum, in a domestic building contract and must do so as soon as practicable after receiving the invoice, receipt or document.
Penalty: 20 penalty units.
Division 5—Other matters