Victorian Consolidated Legislation
[Index]
[Table]
[Search]
[Notes]
[Noteup]
[Previous]
[Next]
[Download]
[Help]
Casino (Management Agreement) Act 1993 - SCHEDULE FIVE
PRELIMINARY ESTIMATE-OFF-SITE EXTERNAL WORKS OPTIONS
Unit Qty Rate Cost
$ $ SUMMARY: 1.00 Modifications to North River Bank
1 401 000 2.00 Kingsway Bridge Abutments and Enhancements (North Side)
476 000 3.00 Low Level Bridge Access Ramps Regrading
1 338 000 4.00 Queensbridge Square Works
3 641 000 5.00 Queensbridge Square Tunnel Access
4 309 000 6.00 Whiteman Street Upgrade Works
2 904 000 7.00 Clarendon Street Plaza
511 000 8.00 Power Street Extension Roadworks
719 000 9.00 Kingsway South Access Ramps
8 000 000
TOTAL ESTIMATED COST
23 299 000 EXCLUSIONS: The following items have not been included in the above
preliminary cost assessment:
(i) Capital or operating costs of the tram link proposed for Whiteman
Street;
(ii) Private Land Acquisition and Transaction Costs; (iii) Performance
Guarantees; (iv) Interest;
(v) Finance Charges and Establishment.
PRELIMINARY ESTIMATE-OFF-SITE EXTERNAL WORKS OPTIONS-continued Sch. 1
Unit Qty Rate Cost
$ $ 1.00 Modifications to North River Bank
1.01 Construct 2 metre wide timber wharf/pier like structure along river bank
at current river edge alignment
m
480
1 500
720 000
-blue stone steps Item
80 000 1.02 Pedestrian Promenade Sunday market paving
m2
1 440
125
180 000 1.03 Boat mooring facilities and fittings to wharf
Item
10 000 1.04 Landscaping, grassing and planting including gravel paths
Item
150 000 1.05 External seating and civic furniture
Item
50 000 1.06 External lighting poles Item
45 000
1 235 000
Contingency 5%
62 000
Design Fees 8%
104 000
Total Modifications to North River Bank 1 401 000
PRELIMINARY ESTIMATE-OFF-SITE EXTERNAL WORKS OPTIONS-continued Sch. 1
Unit Qty Rate Cost
$ $ 2.00 Kingsway Bridge Abutments and Enhancements (North Side)
2.01 Obelisk feature tower at each side of bridge, including special lighting
No.
2
185 000
370 000 2.02 Feature lighting to Kingsway handrails
Item
50 000
420 000
Contingency 5%
21 000
Design Fees 8%
35 000
Total Kingsway Bridge Abutments and Enhancements (North Side)
476 000
PRELIMINARY ESTIMATE-OFF-SITE EXTERNAL WORKS OPTIONS-continued Sch. 1
Unit Qty Rate Cost
$ $ 3.00 Low Level Bridge Access Ramps Regrading
3.01 Jacking and temporary support
No.
2
250 000
500 000 3.02 Demolition and cut-down existing piles and crosshead
No.
2
55 000
110 000 3.03 Reconstruct crosshead and bridge bearing
No.
2
180 000
360 000 3.04 Construct shore access ramps with flood water isolation upstand
walls to RL 2.20
No.
2
85 000
170 000 3.05 Articulated slab between bridge deck and ramps
No.
2
20 000
40 000
1 180 000
Contingency 5%
59 000
Design Fees 8%
99 000
Total Low Level Bridge Access Ramps Regrading 1 338 000
PRELIMINARY ESTIMATE-OFF-SITE EXTERNAL WORKS OPTIONS-continued Sch. 1
Unit Qty Rate Cost
$ $ 4.00 Queensbridge Square Works
4.01 Beacon Towers No. 3 185 000 555 000 4.02 Roadway reconstruction including
kerbs and channels
m2
5 120
90
460 800 4.03 Plaza paving with bluestone bands and granite sets
m2
6 080
225
1 368 000 4.04 Landscaping, planting and trees
Item
120 000 4.05 Realignment of tram tracks in Queensbridge Street between river
and Whiteman/Power Streets-
Dual track m 250 1 100 275 000
Overhead electrical m 250 300 75 000
Safety zone Item
15 000
PTC Design and Management
18%
65 700 4.06 Traffic signals Queensbridge Square
Item
200 000 4.09 Civic furniture including seats, rubbish bins, information boards
and bollards
Item
50 000 4.10 External lighting poles
Item
25 000
3 210 000
Contingency 5%
161 000
Design Fees 8%
270 000
Total Queensbridge Square Works 3 641 000
PRELIMINARY ESTIMATE-OFF-SITE EXTERNAL WORKS OPTIONS-continued Sch. 1
Unit Qty Rate Cost
$ $ 5.00 Queensbridge Square Tunnel Access
The following works are additional to the works included in item 4 above
5.01 Additional services diversions and relocations including water, gas,
electricity and Telecom
Item
1 500 000 5.02 Dual lane vehicle tunnel approximately 180 metres long from
Casino and exiting in South Bank Boulevard. (Tunnel constructed by cut and
cover method)
Item
1 850 000 5.03 Traffic lights, tunnel exit/entry in Southbank Boulevard
Item
100 000 5.04 Additional roadworks to Southbank Boulevard
Item
350 000
3 800 000
Contingency 5%
190 000
Design Fees 8%
319 000
Total Queensbridge Square Tunnel Access 4 309 000
PRELIMINARY ESTIMATE-OFF-SITE EXTERNAL WORKS OPTIONS-continued Sch. 1
Unit Qty Rate Cost
$ $ 6.00 Whiteman Street Upgrade Works
6.01 Reconstruct road pavement including bluestone kerbs and channels
m2
7 500
125
937 500 6.02 New bluestone pedestrian paving with granite bands
m2
2 400
145
348 000 6.03 Bluestone and granite feature to roadway at Casino entrance
m2
2 500
200
500 000 6.04 Street lighting and poles Item
35 000 6.05 Traffic signals Queensbridge Street/Power Street intersection
Item
200 000 6.06 Traffic signals Clarendon Street intersection
Item
200 000 6.07 Traffic signals basement carpark entry/exit
Item
200 000 6.08 Landscaping and street trees
Item
120 000 6.09 Civic furniture including seats, rubbish bins and information
boards
Item
20 000
2 560 500
Contingency 5%
128 000
Design Fees 8%
215 000
Total Whiteman Street Upgrade Works 2 904 000
PRELIMINARY ESTIMATE-OFF-SITE EXTERNAL WORKS OPTIONS-continued Sch. 1
Unit Qty Rate Cost
$ $ 7.00 Clarendon Street Plaza
7.01 Roadway plaza paving incorporating light coloured granite bands
m2
3 000
125
375 000 7.02 Landscaping (including trees) Item
25 000 7.03 Pedestrian operated traffic lights
Item
40 000 7.04 Civic furniture, bollards etc. Item
10 000
450 000
Contingency 5%
23 000
Design Fees 8%
38 000
Total Clarendon Street Plaza 511 000
PRELIMINARY ESTIMATE-OFF-SITE EXTERNAL WORKS OPTIONS-continued Sch. 1
Unit Qty Rate Cost
$ $ 8.00 Power Street Extension Roadworks
8.01 Reconstruct road pavement including new concrete kerbs and channels
m2
3 750
90
337 500 8.02 New concrete pedestrian paving
m2
900
35
31 500 8.03 Overhead street lighting and poles
Item
15 000 8.04 Landscaping and street trees Item
45 000 8.05 Civic furniture Item
5 000 8.06 Traffic signals Power Street/City Road intersection
Item
200 000
634 000
Contingency 5%
32 000
Design Fees 8%
53 000
Total Power Street Extension Roadworks 719 000
PRELIMINARY ESTIMATE-OFF-SITE EXTERNAL WORKS OPTIONS-continued Sch. 1
Unit Qty Rate Cost
$ $ 9.00 Kingsway South Access Ramps
9.01 Dual lane access ramps each side of Kingsway bridge providing access from
Whiteman Street for southern access to Kingsway
Item
8 000 000
8 000 000
Contingency
incl.
Design Fees
incl.
Total Kingsway South Access Ramps 8 000 000
EXECUTED as an agreement.
SIGNED by the Honourable HADDON STOREY, QC MLC for and on behalf of THE STATE
OF VICTORIA in the presence of- ü ý þ HADDON STOREY Hon. Haddon Storey, QC MLC
Signature of Witness KARIN PUELS
Name of Witness (please print) KARIN PUELS
THE COMMON SEAL of CROWN CASINO LTD. is affixed in accordance with its
articles of association in the presence of- ü ý þ LS PETER JONSON Signature of
Secretary/Director PETER JONSON Name of Secretary/Director (please print)
B. J. HAMILTON Signature of Director BARRY J. HAMILTON Name of Director
(please print) __________________
[Index]
[Table]
[Search]
[Notes]
[Noteup]
[Previous]
[Next]
[Download]
[Help]