Building Act 1993 - SECT 60
Reporting authority to be notified of occupancy permit
60. Reporting authority to be notified of occupancy permit
If the relevant building surveyor issues an occupancy permit under this
Division which differs from or fails to implement the recommendations in a
reporting authority's report under Schedule 2 on the application for the
permit, the relevant building surveyor must notify the reporting authority
without delay of the permit and give the reporting authority a copy of the
permit.