BUILDING ACT 1993 - SECT 182C

Ending show cause process without further action

If the Authority no longer believes a ground exists to take disciplinary action against the registered building practitioner, the Authority

        (a)     must take no further action about the show cause notice; and

        (b)     must revoke any suspension under section 180A(1) that relates to the matter that is the subject of the show cause notice; and

        (c)     must, as soon as practicable after making its decision, give notice to the registered building practitioner that no further action will be taken about the show cause notice.

S. 182D inserted by No. 15/2016 s. 25, amended by No. 46/2018 s. 50(1)(2) (ILA s. 39B(1)).