Victorian Bills[Index] [Search] [Download] [Related Items] [Help]
This is a Bill, not an Act. For current law, see the Acts databases.
PARLIAMENT OF VICTORIA
Mineral Resources Development (Sustainable
Development) Act 2006
Act No.
TABLE OF PROVISIONS
Clause Page
PART 1--PRELIMINARY 1
1. Purposes 1
2. Commencement 2
3. Principal Act 3
PART 2--AMENDMENTS TO THE MINERAL RESOURCES
DEVELOPMENT ACT 1990 4
4. Change of title 4
5. New section 2A inserted 4
2A. Principles of sustainable development 4
6. Definitions 6
7. Division 1 of Part 2 7
8. Division 2 of Part 2 and new section 14AB 7
Division 2--Licence process 7
14AB. Application of this Division 7
9. Application for a licence 7
10. Notice of applications with priority 7
11. Grant or refusal of licence 8
12. New Division 3 of Part 2 inserted 9
Division 3--Licence process for direct allocation of licences
relating to coal 9
Subdivision 1--General 9
26AA. Definition 9
26AB. Licence applications under Division to be in respect of
exempted land 9
Subdivision 2--Licences granted by the Minister 9
26AC. Who may apply for a licence under this Subdivision? 9
26AD. Application procedure 10
26AE. Application of Act to licence application 11
i
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Clause Page
26AF. Grant or refusal of licence 11
26AG. Revocation of exemption over licence land 12
26AH. Minister must publish notice 12
26AI. Application of Act to licence 13
Subdivision 3--Licences granted by the Governor in
Council 13
26AJ. Application procedure 13
26AK. Notification and advertising requirements 14
26AL. Application of Act to licence application 15
26AM. Grant or refusal of licence 15
26AN. Minister must publish reasons for refusal to grant
licence 17
26AO. Revocation of exemption over licence land 17
26AP. Minister must publish notice 17
26AQ. Application of Act to licence 18
13. Division 4 of Part 2 18
14. Update of references to Australian Property Institute 18
15. New Division 5 of Part 2 inserted 19
Division 5--Tenders for licences 19
27. Tendering process 19
27A. Acceptance of tender 19
27B. Advertising and notice requirements 20
27C. Consultation and notification requirements 20
27D. Application of provisions to tenders 21
27E. Minister may not accept any tenders 21
16. Repeal of section 28 22
17. Division 6 of Part 2 22
18. Application for renewal of licence 22
19. Division 7 of Part 2 22
20. Variation of licence 22
21. Amalgamation of licences 23
22. Division 8 of Part 2 23
23. Cancellation of licence 23
24. Work must be approved 23
25. New section 39A inserted 24
39A. Licensee's duty to consult with community 24
26. Work plan 24
27. Variation of work plan on application of a licensee 25
28. Department Head may direct variation of work plan 27
29. Minister may require impact statement 27
30. Commencement of work under mining licence 28
31. Commencement of work under exploration licence 28
32. Particular consents etc. required 29
ii
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Clause Page
33. Protection of buildings and sites 29
34. New section 45A inserted 32
45A. Certain exploration and mining work complies with
section 45 32
35. Minister may limit protection 33
36. New section 47 inserted 34
47. New consent or authorisation for certain work plan
variations 34
37. New Part 4A inserted 36
PART 4A--ADVISORY PANELS 36
Division 1--Appointment of panels 36
54A. Appointment of advisory panels 36
54B. Composition of panel 36
54C. Chairperson 36
54D. Terms of reference 36
54E. Terms and conditions of appointment 36
Division 2--Procedure of panels 37
54F. Procedure of panel 37
54G. Directions about hearings 37
54H. Hearings to be in public 37
54I. Procedure for hearing submissions 38
54J. Adjournment of hearings 38
54K. Panel may regulate its own proceedings 38
54L. Panel may take into account any relevant matter 38
54M. Report of panel 39
38. Functions of Department Head 39
39. Disclosure of registered information 40
40. New section 77A inserted 40
77A. Definition 40
41. New section 79A inserted 40
79A. Rehabilitation liability assessment 40
42. Rehabilitation bond 41
43. Rehabilitation 41
44. New section 81A inserted 42
81A. Certification that land has been rehabilitated 42
45. New Part 8A inserted 42
PART 8A--CODES OF PRACTICE 42
89A. Power to make Codes of Practice 42
89B. Variation and revocation of Code of Practice 43
89C. Advertising of draft Code of Practice, variation or
revocation 43
89D. Consideration of submissions 44
89E. How is a Code of Practice made? 44
iii
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Clause Page
89F. Availability of Code of Practice 45
89G. Breach of Code of Practice not an offence 45
89H. Use of Code of Practice in proceedings 45
46. Division 1 of Part 9 46
47. Delegation 46
48. New section 92 substituted 47
92. Identity cards 47
49. New Divisions 2 to 11 inserted and substituted for section 93 47
Division 2--Performance of functions or exercise of powers 47
93. Inspectors subject to Department Head's directions 47
Division 3--Powers relating to entry 48
94. Power to enter 48
95. General powers on entry 48
95A. Power to require production of documents etc. 49
95B. Power to take samples 50
Division 4--Procedure relating to entry 51
95C. Announcement on entry 51
95D. Report to be given about entry 51
Division 5--Search warrants 52
95E. Definition 52
95F. Issue of search warrants 53
95G. Announcement before entry on warrant 54
95H. Copy of warrant to be given to occupier 55
Division 6--Limitation on entry powers 55
95I. Places used for residential purposes 55
Division 7--Return and forfeiture of seized things 55
95J. Return of seized things 55
95K. Forfeiture of seized things 56
Division 8--Other powers 57
95L. Power to require name and address 57
95M. Power to give directions 58
Division 9--Other matters 58
95N. Occupier must assist inspector 58
95O. Other assistance in exercising powers 58
95P. Inspector may take affidavits 59
95Q. Inspector may copy documents 59
iv
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Clause Page
Division 10--Offences 60
95R. Offences in relation to inspections 60
Division 11--Protection of privileges 61
95S. Protection against self-incrimination 61
95T. Legal professional privilege not affected 61
50. New section 105 inserted 61
105. Annual report 61
51. Order to cease work 62
52. New section 110A inserted 63
110A. Enforcement order 63
53. New section 120A inserted 64
120A. Ministerial guidelines 64
54. Regulations 64
55. New sections 133 and 134 inserted 64
133. Validation of certain exploration and mining work--
2006 amendments 64
134. Change of title provision--2006 amendments 65
56. New section 135 inserted 66
135. Transitional provision--2006 amendments 66
57. Amendment of Schedule 1 66
58. Amendment of Schedule 3 66
PART 3--AMENDMENTS TO OTHER ACTS 67
Division 1--Amendments to the Environment Protection Act 1970 67
59. Appointment of environmental auditor 67
60. Offences 67
Division 2--Amendments to Other Acts 68
61. Consequential amendments 68
__________________
SCHEDULE--Consequential Amendments to Other Acts 69
ENDNOTES 75
v
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
PARLIAMENT OF VICTORIA
A BILL
to amend the Mineral Resources Development Act 1990 and the
Environment Protection Act 1970 and to make consequential
amendments to other Acts and for other purposes.
Mineral Resources Development
(Sustainable Development) Act 2006
The Parliament of Victoria enacts as follows:
PART 1--PRELIMINARY
1. Purposes
The main purposes of this Act are--
(a) to amend the Mineral Resources
Development Act 1990--
5
(i) to rename that Act; and
1
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 1--Preliminary
s. 2
(ii) to provide for exploration or mining
work in prohibited areas; and
(iii) to require licensees to carry out
community consultation; and
(iv) to require licensees to offset the
5
environmental impact of exploration or
mining work; and
(v) to provide further for the rehabilitation
of land affected by exploration or
mining work; and
10
(vi) to provide for the direct allocation of
licences relating to coal; and
(vii) to include sustainable development
principles; and
(viii) to provide for the appointment of
15
panels to advise the Minister; and
(ix) to provide for the making of codes of
practice; and
(x) to provide for further inspection
powers; and
20
(xi) to make other amendments to that Act
to improve its efficiency and operation;
and
(b) to make consequential amendments to the
Environment Protection Act 1970 and to
25
other Acts.
2. Commencement
(1) This Act (except sections 6(2), 26(2), 27(4), 28
and 56) comes into operation on the day after the
day that it receives the Royal Assent.
30
(2) Subject to sub-section (3), sections 6(2), 26(2),
27(4), 28 and 56 come into operation on a day or
days to be proclaimed.
2
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 1--Preliminary
s. 3
(3) If a provision referred to in sub-section (2) does
not come into operation before 1 October 2007, it
comes into operation on that day.
3. Principal Act
See:
In this Act, the Mineral Resources Development
5 Act No.
Act 1990 is called the Principal Act. 92/1990.
Reprint No. 6
as at
1 January
2006
and
amending
Act Nos
16/2006,
29/2006 and
32/2006.
LawToday:
www.dms.
dpc.vic.
gov.au
__________________
3
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 4
PART 2--AMENDMENTS TO THE MINERAL RESOURCES
DEVELOPMENT ACT 1990
4. Change of title
In the title of the Principal Act, for
"Development" substitute "(Sustainable
5
Development)".
5. New section 2A inserted
After section 2 of the Principal Act insert--
"2A. Principles of sustainable development
(1) It is the intention of Parliament that in the
10
administration of this Act regard should be
given to the principles of sustainable
development.
(2) For the purposes of this Act, the principles of
sustainable development are--
15
(a) community wellbeing and welfare
should be enhanced by following a path
of economic development that
safeguards the welfare of future
generations;
20
(b) there should be equity within and
between generations;
(c) biological diversity should be protected
and ecological integrity maintained;
(d) there should be recognition of the need
25
to develop a strong, growing,
diversified and internationally
competitive economy that can enhance
the capacity for environment
protection;
30
4
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 5
(e) measures to be adopted should be cost
effective and flexible, not
disproportionate to the issues being
addressed, including improved
valuation, pricing and incentive
5
mechanisms;
(f) both long and short term economic,
environmental, social and equity
considerations should be effectively
integrated into decision-making;
10
(g) if there are threats of serious or
irreversible environmental damage,
lack of full scientific certainty should
not be used as a reason for postponing
measures to prevent environmental
15
degradation and decision-making
should be guided by--
(i) a careful evaluation to avoid
serious or irreversible damage to
the environment wherever
20
practicable; and
(ii) an assessment of the risk-weighted
consequences of various options;
(h) development should make a positive
contribution to regional development
25
and respect the aspirations of the
community and of Indigenous peoples;
(i) decisions and actions should provide
for community involvement in issues
that affect them.".
30
5
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 6
6. Definitions
(1) In section 4(1) of the Principal Act--
(a) in the definition of "owner", for
paragraph (a) substitute--
"(a) in relation to Crown land, means the
5
Crown land Minister; and";
(b) in the definition of "worksite" after "tourist
mine authority" insert "or where
rehabilitation work is being done, or required
to be done, under Part 7";
10
(c) insert the following definitions--
' "Code of Practice" means a Code of
Practice made under Part 8A as
amended and in force for the time
being;
15
"Crown land Minister" in relation to
Crown land, means the Minister
responsible for administering the Act
under which the land is controlled or
managed;
20
"rehabilitation bond" means a
rehabilitation bond referred to in
section 80;
"rehabilitation plan" means a rehabilitation
plan referred to in section 79;'.
25
(2) In section 4(1) of the Principal Act insert the
following definition--
' "community engagement plan" has the
meaning set out in section 40(3)(b)(ii);'.
(3) Section 4(3) of the Principal Act is repealed.
30
6
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 7
7. Division 1 of Part 2
Before section 13 of the Principal Act insert the
following heading--
"Division 1--General licence provisions".
8. Division 2 of Part 2 and new section 14AB
5
After section 14A of the Principal Act insert--
"Division 2--Licence process
14AB. Application of this Division
The provisions in this Division do not apply
to a licence for which an application may be
10
made under Division 3 unless specifically
applied under Division 3.".
9. Application for a licence
In section 15 of the Principal Act--
(a) sub-section (1A)(g) is repealed;
15
(b) in sub-section (5A), for "Ministers
administering the Crown Land (Reserves)
Act 1978 and the Forests Act 1958 in
relation to the carrying out of work on that
land and those Ministers" substitute "Crown
20
land Minister in relation to the carrying out
of work on that land and the Crown land
Minister".
10. Notice of applications with priority
(1) Insert the following heading to section 18 of the
25
Principal Act--
"Notice of applications with priority".
7
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 11
(2) In section 18 of the Principal Act--
(a) in paragraph (b), for "Commonwealth."
substitute "Commonwealth; and";
(b) after paragraph (b) insert--
"(c) if the application is for a mining
5
licence, the Executive Director (within
the meaning of the Heritage Act
1995).".
11. Grant or refusal of licence
(1) In section 25(1)(g) of the Principal Act, for
10
"applicant is" substitute "licence is granted to".
(2) In section 26(2) of the Principal Act--
(a) after paragraph (c) insert--
"(d) providing and implementing
environmental offsets on the land or
15
any other land;";
(b) in paragraph (j), for "stratum." substitute
"stratum;";
(c) after paragraph (j) insert--
"(k) protection of community facilities.".
20
(3) After section 26(8) of the Principal Act insert--
"(9) On the registration of the grant of a mining
licence, any land covered by that licence that
was, immediately before the registration,
covered by an exploration licence ceases to
25
be covered by that exploration licence.".
8
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 12
12. New Division 3 of Part 2 inserted
After section 26 of the Principal Act insert--
'Division 3--Licence process for direct
allocation of licences relating to coal
Subdivision 1--General
5
26AA. Definition
In this Division, "exempted land" means
land--
(a) that has been exempted under section 7
from being subject to an exploration
10
licence or a mining licence or both; and
(b) that is not subject to an exemption
under section 6.
26AB. Licence applications under Division to be
in respect of exempted land
15
An application for a licence under this
Division may only be made in respect of
exempted land.
Subdivision 2--Licences granted by the
Minister
20
26AC. Who may apply for a licence under this
Subdivision?
A person may apply for a licence under this
Subdivision only if the Minister is satisfied
that--
25
(a) the person was a successful tenderer
under a prior competitive process
equivalent to the tender process under
section 27; and
9
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 12
(b) in order to implement the requirements
of the tender, the person requires access
to coal.
26AD. Application procedure
(1) A person may apply to the Minister in
5
accordance with the regulations for a licence
to carry out the exploration or mining of coal
on exempted land.
(2) Sections 15(1C), 15(2), 15(6), 15(7) and
15(8) apply to an application under this
10
Subdivision as if the application were made
under Division 2.
(3) If the Minister accepts an application, he or
she must notify the applicant in writing that
the application has been accepted.
15
(4) An applicant for a licence must, within
14 days after being notified under sub-
section (3) that the application has been
accepted--
(a) advertise the application in accordance
20
with the regulations; and
(b) if the application is for a mining
licence, give notice of it in accordance
with the regulations to the owner and
occupier of the land affected.
25
(5) The Minister must, as soon as practicable
after an applicant for a licence covering
unrestricted Crown land is notified under
sub-section (3) that the application has been
accepted, consult with the Crown land
30
Minister in relation to the carrying out of
work on that land and the Crown land
Minister may recommend to the Minister
conditions to which the licence should be
made subject.
35
10
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 12
(6) Until regulations are made for the purposes
of sub-sections (1) and (4), the relevant
regulations relating to applications for
licences under Division 2 will apply (with
any necessary modifications).
5
26AE. Application of Act to licence application
(1) Sections 17, 19 and 24 apply to an
application under this Subdivision as if the
application were made under Division 2.
(2) The Department Head must, within 14 days
10
after an applicant for a licence is notified
under section 26AD(3) that the application
has been accepted, give notice of the
application to the persons and bodies
referred to in section 18.
15
26AF. Grant or refusal of licence
(1) The Minister must not grant a licence over
land--
(a) that is exempted under section 6 of this
Act or under any other Act from being
20
subject to--
(i) an exploration licence, if the
application is for an exploration
licence; or
(ii) a mining licence, if the application
25
is for a mining licence; or
(b) that is subject to a current minerals
exemption; or
(c) that is limited to a particular stratum
unless the Minister is satisfied that the
30
applicant can obtain reasonable access
to and use of the land.
11
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 12
(2) Otherwise, the Minister may grant or refuse
a licence after considering any objections
made under section 24 as applied by
section 26AE.
(3) Sections 25(3), 25(4) and 25(7) apply to the
5
granting of a licence under this Subdivision
as if the decision to grant or refuse to grant
the licence were made under Division 2.
(4) Sections 26(1), 26(2), 26(4), 26(4A) and
26(8) apply to a licence granted under this
10
Subdivision as if the licence were granted
under Division 2.
26AG. Revocation of exemption over licence land
On the granting of a licence under this
Subdivision the exemption to which the area
15
of land covered by the licence is subject
under section 7(1) is revoked to the extent
that it relates to that land.
26AH. Minister must publish notice
The Minister must cause a notice to be
20
published in the Government Gazette--
(a) stating that a licence under this
Subdivision has been granted; and
(b) describing the area of land covered by
the licence; and
25
(c) stating that the exemption relating to
the area of land covered by the licence
is revoked to the extent that it relates to
that land.
12
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 12
26AI. Application of Act to licence
(1) On the granting of a licence under this
Subdivision, this Act (except Divisions 2
and 5 of this Part) applies to the licence as if
it were granted by the Minister under
5
Division 2.
(2) Without limiting sub-section (1), the
following things may be done under this Part
in relation to the licence--
(a) the licence may be renewed,
10
transferred, varied, surrendered,
cancelled or amalgamated with another
licence;
(b) a condition of the licence may be
varied, suspended, revoked or added;
15
(c) the area of land covered by the licence
may be excised, transferred or
cancelled in part.
Subdivision 3--Licences granted by the
Governor in Council
20
26AJ. Application procedure
(1) A person may apply in accordance with the
regulations for the Governor in Council to
grant a licence to carry out the exploration or
mining of coal on exempted land on the basis
25
that the application is of State interest.
(2) The application must be made to the Minister
and be accompanied by evidence setting out
the grounds for the application to be
considered as one of State interest.
30
(3) An application for a licence is ineffective,
and must not be accepted by the Minister
unless it is made in accordance with the
regulations and sub-section (2).
13
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 12
(4) Sections 15(2), 15(6), 15(7) and 15(8) apply
to an application under this Subdivision as if
the application were made under Division 2.
26AK. Notification and advertising requirements
(1) If the Minister is not satisfied that the
5
application is of State interest he or she must
notify the applicant in writing of that fact
setting out the reasons for not being so
satisfied.
(2) If the Minister is satisfied that the application
10
is of State interest, he or she must notify the
applicant in writing that the application is of
State interest.
(3) An applicant for a licence must, within
14 days after being notified under sub-
15
section (2) that the application is of State
interest--
(a) advertise the application in accordance
with the regulations; and
(b) if the application is for a mining
20
licence, give notice of it in accordance
with the regulations to the owner and
occupier of the land affected.
(4) The Minister must, as soon as practicable
after an applicant for a licence covering
25
unrestricted Crown land is notified under
sub-section (2) that the application is of State
interest, consult with the Crown land
Minister in relation to the carrying out of
work on that land and the Crown land
30
Minister may recommend to the Minister
conditions to which the licence should be
made subject.
14
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 12
(5) Until regulations are made for the purposes
of section 26AJ(1) and sub-section (3), the
relevant regulations relating to applications
for licences under Division 2 will apply
(with any necessary modifications).
5
26AL. Application of Act to licence application
(1) Sections 17, 19 and 24 apply to an
application under this Subdivision as if the
application were made under Division 2.
(2) The Department Head must, within 14 days
10
after an applicant for a licence is notified
under section 26AK(2) that the application is
of State interest, give notice of the
application to the persons and bodies
referred to in section 18.
15
26AM. Grant or refusal of licence
(1) The Governor in Council must not grant a
licence over land--
(a) that is exempted under section 6 of this
Act or under any other Act from being
20
subject to--
(i) an exploration licence, if the
application is for an exploration
licence; or
(ii) a mining licence, if the application
25
is for a mining licence; or
(b) that is subject to a current minerals
exemption; or
(c) that is limited to a particular stratum
unless the Governor in Council, on the
30
recommendation of the Minister, is
satisfied that the applicant can obtain
reasonable access to and use of the
land.
15
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 12
(2) Otherwise, the Governor in Council on the
recommendation of the Minister may--
(a) grant a licence under this section to an
applicant to carry out the exploration or
mining of coal on exempted land; or
5
(b) refuse to grant that licence.
(3) The Minister must not make a
recommendation under sub-section (2)
unless the Minister has first considered any
objections made under section 24 as applied
10
by section 26AL(1).
(4) Sections 25(3), 25(4) and 25(7) apply to the
granting or refusal of the granting of a
licence under this Subdivision as if--
(a) the decision to grant or refuse to grant
15
the licence were made under
Division 2; and
(b) any reference to the Minister were a
reference to the Governor in Council on
the recommendation of the Minister.
20
(5) Sections 26(1), 26(2), 26(4), 26(4A) and
26(8) apply to a licence granted under this
Subdivision as if--
(a) the licence were granted under
Division 2; and
25
(b) any reference to the Minister were a
reference to the Governor in Council on
the recommendation of the Minister.
16
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 12
26AN. Minister must publish reasons for refusal
to grant licence
If the Governor in Council, on the
recommendation of the Minister, refuses to
grant a licence under this Subdivision, the
5
Minister must publish a notice setting out the
reasons for the refusal in--
(a) the Government Gazette; and
(b) a newspaper circulating generally
throughout the State.
10
26AO. Revocation of exemption over licence land
On the granting of a licence under this
Subdivision the exemption to which the area
of land covered by the licence is subject
under section 7(1) is revoked to the extent
15
that it relates to that land.
26AP. Minister must publish notice
(1) The Minister must cause a notice to be
published in the Government Gazette--
(a) stating that a licence under this
20
Subdivision has been granted; and
(b) stating the reasons for granting the
licence; and
(c) describing the area of land covered by
the licence; and
25
(d) stating that the exemption relating to
the area of land covered by the licence
is revoked to the extent that it relates to
that land.
(2) The Minister must also cause a notice setting
30
out the reasons for granting the licence to be
published in a newspaper circulating
generally throughout the State.
17
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 13
26AQ. Application of Act to licence
(1) On the granting of a licence under this
Subdivision, this Act (except Divisions 2
and 5 of this Part) applies to the licence as if
it were granted by the Minister under
5
Division 2.
(2) Without limiting sub-section (1), the
following things may be done under this Part
in relation to the licence--
(a) the licence may be renewed,
10
transferred, varied, surrendered,
cancelled or amalgamated with another
licence;
(b) a condition of the licence may be
varied, suspended, revoked or added;
15
(c) the area of land covered by the licence
may be excised, transferred or
cancelled in part.'.
13. Division 4 of Part 2
Before section 26A of the Principal Act insert the
20
following heading--
"Division 4--Requirements if agricultural land
covered by mining licence".
14. Update of references to Australian Property
Institute
25
In sections 26C(1)(c), 26D(1) and 26D(5) of the
Principal Act, for "Australian Institute of Valuers
and Land Economists" substitute "Australian
Property Institute".
18
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 15
15. New Division 5 of Part 2 inserted
For section 27 of the Principal Act substitute--
'Division 5--Tenders for licences
27. Tendering process
(1) The Minister may invite tenders for a licence
5
over land that is not the subject of a licence
or an application for a licence.
(2) A tender for a licence is ineffective if it does
not contain the information required by the
regulations for the purposes of this section.
10
(3) A tender for a licence may be over land that
has been exempted under section 7 from
being subject to an exploration licence or a
mining licence, or both.
27A. Acceptance of tender
15
(1) If the Minister accepts a tender, he or she
must notify the successful tenderer in writing
that the tender has been accepted.
(2) On the Minister accepting a tender for a
licence that covers an area of land all or part
20
of which is subject to an exemption under
section 7(1)--
(a) the exemption is revoked to the extent
that it relates to the area of land; and
(b) the Minister must cause a notice to be
25
published in the Government Gazette--
(i) stating that the tender has been
accepted; and
(ii) describing the area of land subject
to the exemption; and
30
19
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 15
(iii) stating that the exemption relating
to the area of land is revoked to
the extent that it relates to that
land.
27B. Advertising and notice requirements
5
(1) A successful tenderer, within 14 days after
being notified under section 27A(1) that the
tender has been accepted, must--
(a) advertise the acceptance of the tender in
accordance with the regulations; and
10
(b) if the tender is for a mining licence,
give notice of the acceptance of the
tender in accordance with the
regulations to the owner and occupier
of the land to be affected by the licence.
15
(2) Until regulations are made for the purposes
of sub-section (1) the relevant regulations
relating to applications for licences under
Division 2 will apply (with any necessary
modifications).
20
27C. Consultation and notification
requirements
(1) The Minister must, as soon as practicable
after a successful tenderer for a licence
covering unrestricted Crown land is notified
25
under section 27A(1) that the tender has been
accepted, consult with the Crown land
Minister in relation to the carrying out of
work on that land and that Minister may
recommend to the Minister conditions to
30
which the licence should be made subject.
(2) The Department Head must, within 14 days
after a successful tenderer is notified under
section 27A(1) that the tender has been
accepted, give notice of the acceptance of the
35
20
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 15
tender to the persons and bodies referred to
in section 18.
27D. Application of provisions to tenders
(1) The application process under Division 2
does not apply to a tender under this
5
Division except as provided in this section.
(2) Sections 24, 25, 25A and 26 apply to a
tender for a licence as if the successful
tenderer were an applicant for the licence.
(3) Without limiting sub-section (2), the
10
Minister must not grant a licence to a person
who has submitted a tender unless the
Minister is satisfied that the person meets the
requirements listed in section 15(6).
27E. Minister may not accept any tenders
15
(1) The Minister may decide not to accept any
tenders for a licence over land that are
submitted in response to an invitation under
this Division.
(2) If the Minister decides not to accept any
20
tender, he or she may invite further tenders
or decide not to call for any more tenders in
relation to that land.
(3) If the Minister decides not to call for any
more tenders in relation to that land, he or
25
she must--
(a) notify the unsuccessful tenderers that
further tenders will not be invited; and
(b) unless the land has been exempted
under section 7 from being subject to
30
an exploration licence or a mining
licence, or both, declare by notice
published in the Government Gazette
that the land is available for
applications for licences.'.
35
21
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 16
16. Repeal of section 28
Section 28 of the Principal Act is repealed.
17. Division 6 of Part 2
Before section 29 of the Principal Act insert the
following heading--
5
"Division 6--Renewals of licences".
18. Application for renewal of licence
(1) For section 29(1) of the Principal Act
substitute--
"(1) A licensee may, before a licence expires,
10
apply in accordance with the regulations to
the Minister for renewal of the licence.".
(2) In section 29(2) of the Principal Act omit
"(whether within the time limit specified in sub-
section (1) or not)".
15
19. Division 7 of Part 2
After section 32 of the Principal Act insert the
following heading--
"Division 7--Changes to licences".
20. Variation of licence
20
(1) Section 34(1A) of the Principal Act is repealed.
(2) In section 34(2) of the Principal Act--
(a) after paragraph (b) insert--
"(ba) if the Minister decides it is necessary to
ensure that appropriate environmental
25
offsets are provided for or
implemented; or";
22
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 21
(b) for paragraph (c) substitute--
"(c) if the Minister decides it is necessary
for the protection of a community
facility; or";
(c) in paragraph (cb), for "section 40(4)(a)"
5
substitute "section 40(6) or 41(5)".
(3) Section 34(2A) of the Principal Act is repealed.
21. Amalgamation of licences
After section 36(4) of the Principal Act insert--
"(4A) On an amalgamation of licences coming into
10
effect the term of the licence nominated
under sub-section (2) is to be the term of
whichever of the amalgamated licences is to
expire first.".
22. Division 8 of Part 2
15
After section 36A of the Principal Act insert the
following heading--
"Division 8--Surrender and cancellation of
licences".
23. Cancellation of licence
20
(1) In section 38(1)(b)(i)(B) of the Principal Act, after
"licence" insert "or the work plan".
(2) Section 38(2) of the Principal Act is repealed.
24. Work must be approved
(1) After section 39(1)(a) of the Principal Act
25
insert--
"(ab) in accordance with the approved work plan;
or".
(2) In section 39(4)(b) of the Principal Act, for
"43(1)(b) to (e)" substitute "43(1)(c), (cb)
30
and (e)".
23
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 25
25. New section 39A inserted
After section 39 of the Principal Act insert--
"39A. Licensee's duty to consult with community
A licensee has a duty to consult with the
community throughout the period of the
5
licence by--
(a) sharing with the community
information about any activities
authorised by the licence that may
affect the community; and
10
(b) giving members of the community a
reasonable opportunity to express their
views about those activities.".
26. Work plan
(1) For section 40(2A) of the Principal Act
15
substitute--
"(2A) In the case of a mining licence, if any part of
the land relating to the work plan is Crown
land, the Department Head must without
delay lodge a copy of the work plan with the
20
Crown land Minister.
(2B) Sub-section (2A) does not apply if the only
work set out in the work plan that is
proposed to be done on the Crown land is
exploration work.".
25
(2) For section 40(3) of the Principal Act
substitute--
'(3) A work plan must contain--
(a) the prescribed information; and
(b) if the licence is a mining licence--
30
(i) a rehabilitation plan for the area of
land covered by the licence; and
24
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 27
(ii) in relation to the mining activities
proposed to be carried out under
the licence, a plan for consulting
with the community prepared in
accordance with the regulations
5
and any guidelines issued by the
Minister relating to such plans
(a "community engagement
plan").'.
(3) For section 40(3A) of the Principal Act
10
substitute--
"(3A) Within 28 days after a copy of the work plan
is lodged with the Crown land Minister, or
any longer period allowed by the Minister,
the Crown land Minister--
15
(a) must give comments to the Minister on
the rehabilitation plan included in the
work plan; and
(b) may recommend changes to be made to
the work plan before it is approved or
20
conditions to which an approval should
be made subject.".
(4) For section 40(4)(e) of the Principal Act
substitute--
"(e) the Crown land Minister giving the Minister
25
comments under section 40(3A);".
27. Variation of work plan on application of a licensee
(1) After section 41(2) of the Principal Act insert--
"(2A) In the case of a mining licence, if any part of
the land relating to the variation of the work
30
plan is Crown land, the Department Head
must without delay lodge a copy of the
variation to the work plan with the Crown
land Minister.
25
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 27
(2B) Sub-section (2A) does not apply if the only
work set out in the work plan that is
proposed to be done on the Crown land is
exploration work.
(2C) Within 28 days after the variation of the
5
work plan is lodged with the Crown land
Minister, or any longer period allowed by the
Minister, the Crown land Minister--
(a) must give comments to the Minister on
the rehabilitation plan included in the
10
work plan if affected by the variation;
and
(b) may recommend changes to be made to
the variation before it is approved or
conditions to which an approval should
15
be made subject.".
(2) For section 41(3)(e) of the Principal Act
substitute--
"(e) the Crown land Minister giving the Minister
comments under sub-section (2C);".
20
(3) After section 41(5) of the Principal Act insert--
"(5A) The conditions specified under sub-
section (5) may include any of the matters
set out in section 26(2).".
(4) After section 41(8) of the Principal Act insert--
25
"(9) If an application to vary the work plan
consists solely of the inclusion of a
community engagement plan in the work
plan--
(a) the Department Head must give the
30
licensee a written notice approving, or
refusing to approve, or asking for
changes to, the variation of a work plan
within 30 days of receiving the
application; and
35
26
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 28
(b) sub-sections (2A), (2B), (2C), (3), (4),
(6) and (7) do not apply in respect of
the variation.".
28. Department Head may direct variation of work plan
In section 41AA(5) of the Principal Act, for
5
"41(2) to (8)" substitute "41(2) to (9)".
29. Minister may require impact statement
(1) For section 41A(1) of the Principal Act
substitute--
"(1) If the Minister is of the opinion that the
10
proposed exploration work under a work
plan or an application to vary an approved
work plan lodged with the Department Head
by a licensee will have a material impact on
the environment, he or she may, in writing,
15
require the licensee to submit a statement, in
the form specified by the Minister, assessing
the impact of the proposed work on the
environment.".
(2) For section 41A(2) of the Principal Act
20
substitute--
"(2) The Minister must, on receipt of the
statement, forward a copy to--
(a) the Minister administering the
Planning and Environment Act 1987;
25
and
(b) if the proposed work relates to Crown
land, the Crown land Minister--
and request comments on it by the date
specified by the Minister.
30
27
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 30
(3) After section 41A(3) of the Principal Act insert--
"(4) The Minister may seek public comments on
the statement by a specified date and must
consider any comments received by that
date.".
5
30. Commencement of work under mining licence
(1) After section 42(2)(a)(iii) of the Principal Act
insert--
"(iv) has complied with any condition imposed by
the Minister under section 26(2)(d) to
10
provide an environmental offset; and
(v) has obtained the insurance required under
section 39(5); and".
(2) After section 42(2)(a) of the Principal Act
insert--
15
"(ab) any consent under section 45 or authorisation
under section 46 has been registered; and".
(3) In sections 42(5)(a) and 42(7)(c) of the Principal
Act for "Minister" substitute "Department Head".
31. Commencement of work under exploration licence
20
(1) In section 43(1) of the Principal Act--
(a) omit "(other than low impact exploration)";
(b) after paragraph (b) insert--
"(ba) the licensee has complied with any
condition imposed by the Minister
25
under section 26(2)(d) to provide an
environmental offset; and";
28
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 32
(c) after paragraph (c) insert--
"(ca) any consent under section 45 or
authorisation under section 46 has been
registered; and
(cb) the licensee has obtained the insurance
5
required under section 39(5); and".
(2) After section 43(1) of the Principal Act insert--
"(1A) Sub-sections (1)(a), (1)(b), (1)(ba), (1)(ca)
and (1)(d) do not apply to low impact
exploration.".
10
32. Particular consents etc. required
In section 44(1) of the Principal Act, for
"Ministers administering the Crown Land
(Reserves) Act 1978 and the Forests Act 1958"
substitute "Crown land Minister".
15
33. Protection of buildings and sites
(1) Insert the following heading to section 45 of the
Principal Act--
"Prohibition of work near dwellings and
certain places and sites".
20
(2) In section 45(1)(a) of the Principal Act--
(a) after "dwelling house" insert "that existed
before an approved work plan was registered
in respect of the licence";
(b) sub-paragraphs (ii) to (x) are repealed;
25
(c) for sub-paragraph (xii) substitute--
"(xii) any archaeological relic registered
under section 10(a) of the
Archaeological and Aboriginal Relics
Preservation Act 1972; or".
30
29
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 33
(3) For section 45(2) of the Principal Act
substitute--
"(2) A licensee may, with the consent of the
owners of the land on which a dwelling
house is situated, do work within the area
5
prohibited by sub-section (1)(a)(i) in relation
to that dwelling house or within 100 metres
below that area.
(3) A consent given by any owner of land under
sub-section (2)--
10
(a) must be in writing and in the prescribed
form (if any); and
(b) cannot be withdrawn by that owner or
by any subsequent owner of the land;
and
15
(c) binds all subsequent owners and
occupiers of the land.".
(4) In section 45(4A) of the Principal Act, for
"Heritage Council" substitute "Executive
Director (within the meaning of the Heritage Act
20
1995)".
(5) For section 45(5) of the Principal Act
substitute--
"(5) An owner who consents under sub-
section (2), or a person or a body that
25
consents under sub-section (4), (4A) or (4B),
may make the consent conditional on the
following matters only--
(a) specified distance restrictions;
(b) specified depth restrictions.".
30
30
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 33
(6) After section 45(6) of the Principal Act insert--
'(7) In this section--
"dwelling house" means a building that is
used primarily, or is intended, adapted
or designed to be used primarily, as a
5
residence, (including kitchen, bathroom
and sanitary facilities) for an occupier
who has a right to the exclusive use of
it and includes a building that may, in
addition to its primary residential use,
10
be used for small-scale commercial
activities;
"work" means any of the following
activities--
(a) any excavation for the purposes of
15
mining or bulk sampling of ore;
(b) any excavation for the purposes of
exploration using mechanised
equipment;
(c) any construction or use of any
20
opening, excavation, structure or
equipment for access to, or
ventilation of, underground
workings;
(d) any treatment, extraction,
25
handling or processing of minerals
using plant or equipment (other
than hand-operated equipment);
(e) any construction or use of roads
for the haulage of ore, waste rock
30
or overburden;
(f) the bulk storage of ore, waste rock
or overburden;
31
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 34
(g) any construction or use of dams
for the storage of tailings, process
water or groundwater;
(h) any construction or use of other
facilities for the treatment,
5
handling or storage of tailings or
other wastes;
(i) any drilling (unless carried out
with hand-held equipment);
(j) any other activity specified in the
10
regulations--
but does not include the carrying out of
low impact exploration.
(8) For the purposes of sub-section (1)(a)(i) the
distance of 100 metres is to be measured
15
from--
(a) the boundary of the allotment on which
the dwelling house is situated if the
area of the allotment is 04 hectares or
less; or
20
(b) in any other case, a distance of
25 metres from the outer edge of any
eave forming part of the dwelling
house.'.
34. New section 45A inserted
25
After section 45 of the Principal Act insert--
'45A. Certain exploration and mining work
complies with section 45
(1) A licensee who does any work under the
licence within an area of land prohibited by
30
section 45(1)(a)(i) or within 100 metres
below that area complies with section 45 in
respect of that work if--
32
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 35
(a) at the commencement date--
(i) an approved work plan, and, in the
case of a mining licence, a work
authority, was registered in
respect of the licence; and
5
(ii) the approved work plan provided
for that work to be done under the
licence; and
(b) the approved work plan and, in the case
of a mining licence the work authority,
10
is still registered at the time that work is
done; and
(c) that work is done in accordance with
the approved work plan as in effect at
the commencement date.
15
(2) In this section--
"commencement date" means the date of
commencement of section 34 of the
Mineral Resources Development
(Sustainable Development) Act 2006;
20
"work" has the same meaning as it has in
section 45(7).'.
35. Minister may limit protection
(1) Insert the following heading to section 46 of the
Principal Act--
25
"Minister may authorise work near dwelling
house".
(2) In section 46(1) of the Principal Act omit "to (x)".
(3) After section 46(3) of the Principal Act insert--
'(4) In this section "work" has the same
30
meaning as it has in section 45(7).'.
33
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 36
36. New section 47 inserted
After section 46 of the Principal Act insert--
'47. New consent or authorisation for certain
work plan variations
(1) A licensee must obtain a consent under
5
section 45 ("a new consent") to do mining
work ("the new work") that is proposed by
a variation to an approved work plan under
section 41 or 41AA if--
(a) the new work affects all or part of any
10
mining work within an area of land
prohibited by section 45(1), being
mining work--
(i) for which a consent under
section 45 or an authorisation
15
under section 46 is held by the
licensee; or
(ii) that is permitted to be done under
section 45A; and
(b) if the mining work affected by the new
20
work is within an area of land
prohibited by section 45(1)(a)(i), (xi)
or (xii) or within 100 metres below that
area, a permit is required to be obtained
under a planning scheme for the new
25
work; and
(c) if the mining work affected by the new
work is within an area of land
prohibited by section 45(1)(a)(xiii) or
within 100 metres below that area--
30
(i) a permit is required to be obtained
under a planning scheme for the
new work; or
34
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 36
(ii) the new work is excepted under
section 42(7) or 42A from the
requirement to obtain such a
permit.
(2) The Department Head must direct a licensee
5
to obtain consent under section 45 (a "new
consent") to do exploration work ("the new
work") that is proposed by a variation to an
approved work plan under section 41 or
41AA if--
10
(a) the new work affects all or part of any
exploration work within an area of land
prohibited by section 45(1) being
exploration work--
(i) for which a consent under
15
section 45 or an authorisation
under section 46 is held by the
licensee; or
(ii) that is permitted to be done under
section 45A; and
20
(b) the Department Head considers that the
new work will result in significant
changes to that exploration work.
(3) In this section "work" has the same
meaning as it has in section 45(7).
25
(4) This section applies despite section 45A.'.
35
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 37
37. New Part 4A inserted
After Part 4 of the Principal Act insert--
"PART 4A--ADVISORY PANELS
Division 1--Appointment of panels
54A. Appointment of advisory panels
5
The Minister may appoint a panel to consider
and advise on any matter relating to
exploration, mining, or the administration of
this Act, referred to the panel by the
Minister.
10
54B. Composition of panel
(1) A panel may consist of one or more persons.
(2) In appointing a person to be a member of a
panel, the Minister must be satisfied that the
person has appropriate knowledge, skills or
15
experience.
54C. Chairperson
If a panel consists of more than one member,
the Minister must appoint one of the
members to be the chairperson.
20
54D. Terms of reference
On appointing a panel, the Minister must
specify the terms of reference of the panel.
54E. Terms and conditions of appointment
(1) A member of a panel is appointed for the
25
term that is specified in the instrument of his
or her appointment.
36
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 37
(2) A member of a panel, other than a member
who is employed by or on behalf of the
Crown, is entitled to receive any fees and
allowances fixed by the Minister in the
instrument of his or her appointment.
5
Division 2--Procedure of panels
54F. Procedure of panel
(1) A panel may call for and consider written
submissions from any persons having an
interest in the matter referred to it.
10
(2) A panel may hold a public hearing.
(3) If a panel holds a public hearing, it must give
a reasonable opportunity to be heard by it to
any person who has stated in a written
submission that the person wishes to be
15
heard with respect to that submission.
54G. Directions about hearings
(1) A panel may give directions about--
(a) the times and places of hearings; and
(b) matters preliminary to hearings; and
20
(c) the conduct of hearings.
(2) A panel may refuse to hear any person who
fails to comply with a direction of the panel.
54H. Hearings to be in public
A panel must conduct its hearings in public
25
unless any person making a submission
objects to making the submission in public
and the panel is satisfied that the submission
is confidential in nature.
37
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 37
54I. Procedure for hearing submissions
(1) A person who has a right to be heard by a
panel may--
(a) appear and be heard in person or be
represented by any other person; and
5
(b) give submissions to a panel orally or in
writing or partly orally and partly in
writing.
(2) A panel may report and make
recommendations on a submission without
10
hearing the person who made the submission
if the person is not present or represented at
the time and place appointed for the hearing
of the submission.
(3) A panel may consider 2 or more submissions
15
together if the submissions concern the same
or a related matter.
54J. Adjournment of hearings
A panel may from time to time adjourn a
hearing to any times and places and for any
20
purposes it thinks necessary or just in the
circumstances.
54K. Panel may regulate its own proceedings
A panel may regulate its own proceedings.
54L. Panel may take into account any relevant
25
matter
A panel may take into account any matter it
thinks relevant in making its report and
recommendations.
38
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 38
54M. Report of panel
(1) After considering a matter, including
conducting hearings and considering
submissions under this Part, the panel--
(a) must report to the Minister on the
5
matter; and
(b) may make recommendations in relation
to the matter.
(2) The report of the panel and any
recommendations must be forwarded to the
10
Minister--
(a) if a period is specified in the instrument
of appointment for the forwarding of
the report and any recommendations,
within that period; or
15
(b) in any other case, within 60 days after
the appointment of the panel.".
38. Functions of Department Head
(1) Insert the following heading to section 69 of the
Principal Act--
20
"Functions of Department Head regarding
mining register".
(2) After section 69(1) of the Principal Act insert--
"(1A) The mining register may be kept in
electronic form.".
25
(3) After section 69(2)(a)(iii) of the Principal Act
insert--
"(iiia) consents given under section 45;
(iiib) authorisations given under section 46;".
39
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 39
39. Disclosure of registered information
After section 74(1)(c) of the Principal Act
insert--
"(ca) provide a copy of a registered consent given
under section 45; and
5
(cb) provide a copy of a registered authorisation
given under section 46; and".
40. New section 77A inserted
In Part 7 of the Principal Act before section 78
insert--
10
'77A. Definition
In this Part "auditor" means an
environmental auditor appointed under
section 53S of the Environment Protection
Act 1970.'.
15
41. New section 79A inserted
After section 79 of the Principal Act insert--
'79A. Rehabilitation liability assessment
(1) The Minister may require a licensee to
undertake an assessment of the licensee's
20
rehabilitation liability under section 78
(a "rehabilitation liability assessment") for
the purpose of determining the amount of a
rehabilitation bond or reviewing the amount
of a rehabilitation bond entered into or to be
25
entered into by the licensee.
(2) A rehabilitation liability assessment must--
(a) be undertaken in a manner and form
determined by the Minister; and
(b) take into account works required to be
30
undertaken to rehabilitate the land in
accordance with the requirements of
section 78.
40
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 42
(3) The Minister may require a licensee to
engage an auditor to certify that a
rehabilitation liability assessment has been
prepared in accordance with sub-section (2)
and that it is accurate.
5
(4) An auditor who has given a certification
under sub-section (3) must forward a copy of
the certificate to the Minister within 21 days
after giving that certification.'.
42. Rehabilitation bond
10
For section 80(2) of the Principal Act
substitute--
"(2) If land covered by a mining licence is private
land, the Minister must, before determining
the amount of a rehabilitation bond, consult
15
with--
(a) the council in whose municipal district
the land is situated; and
(b) the owner of the land.".
43. Rehabilitation
20
At the end of section 81 of the Principal Act
insert--
"(2) If the rehabilitation has not been completed
before the licence or renewed licence ceases
to apply to the land the former licensee must
25
complete it as expeditiously as possible.
(3) Section 47A continues to apply to the land
while rehabilitation is completed as if the
former licensee were still a licensee.".
41
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 44
44. New section 81A inserted
After section 81 of the Principal Act insert--
"81A. Certification that land has been
rehabilitated
(1) The Minister may require that a licensee or a
5
former licensee engage an auditor to certify
that land has been rehabilitated as required
by section 78 for the purpose of deciding
whether to return any rehabilitation bond
under section 82.
10
(2) An auditor who has given a certification
under sub-section (1) must forward a copy of
the certificate to the Minister within 21 days
after giving that certification.".
45. New Part 8A inserted
15
After Part 8 of the Principal Act insert--
"PART 8A--CODES OF PRACTICE
89A. Power to make Codes of Practice
(1) The Minister, in accordance with this Part,
may make Codes of Practice that--
20
(a) specify standards and procedures for
the carrying out of any of the objectives
or purposes of this Act or the
regulations made under this Act; and
(b) provide practical guidance to persons
25
on complying with their obligations
under this Act or the regulations made
under this Act.
(2) A Code of Practice may apply, adopt or
incorporate any matter contained in any
30
document, standard, rule, specification or
method, formulated, issued, prescribed or
published by any person whether--
42
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 45
(a) wholly or partially or as amended by
the Code of Practice; or
(b) as formulated, issued, prescribed or
published at the time the Code of
Practice is made or at any time before
5
then; or
(c) as formulated, issued, prescribed or
published from time to time.
89B. Variation and revocation of Code of
Practice
10
The Minister, in accordance with this Part,
may vary or revoke a Code of Practice at any
time.
89C. Advertising of draft Code of Practice,
variation or revocation
15
(1) The Minister must give notice of--
(a) any draft Code of Practice which the
Minister proposes to make;
(b) any variation of a Code of Practice
which the Minister proposes to make;
20
(c) any revocation of a Code of Practice
which the Minister proposes to make.
(2) A notice under sub-section (1) must--
(a) state where a copy of the draft Code of
Practice, variation or revocation (as the
25
case requires) may be obtained; and
(b) state that submissions may be made to
the Minister within 28 days of the
publication of the notice; and
43
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 45
(c) be published--
(i) in the Government Gazette; and
(ii) in a newspaper circulating
generally throughout the State.
(3) Sub-section (1) does not apply to any
5
proposed variation to a Code of Practice--
(a) to correct a clerical mistake; or
(b) to correct an error arising from an
accidental slip or omission; or
(c) to update references.
10
89D. Consideration of submissions
The Minister must consider any submissions
received by the Minister within the time
specified in section 89C(2)(b).
89E. How is a Code of Practice made?
15
(1) After the Minister has considered any
submissions, the Minister may make the
Code of Practice or the variation or
revocation of the Code of Practice.
(2) On the making of a Code of Practice or a
20
variation or revocation of a Code of Practice
the Minister must cause to be published in
the Government Gazette notice of--
(a) the making of the Code of Practice or
the variation or revocation of the Code
25
of Practice; and
(b) in the case of the making of the Code of
Practice or any variation, the place
where copies of the Code of Practice
may be obtained.
30
44
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 45
(3) A Code of Practice or a variation or
revocation of a Code of Practice takes effect
on--
(a) the date that the notice under sub-
section (2) is published in the
5
Government Gazette; or
(b) any later date specified in the notice.
89F. Availability of Code of Practice
A Code of Practice and any documents
incorporated in a Code of Practice must be
10
made available for public inspection free of
charge--
(a) at the principal office of the
Department and major regional offices
of the Department; or
15
(b) in electronic form published on the
Department's Internet site.
89G. Breach of Code of Practice not an offence
A person is not liable to any civil or criminal
proceedings only because the person has
20
failed to observe any provision of a Code of
Practice.
89H. Use of Code of Practice in proceedings
If in any proceeding under this Act it is
alleged that a person contravened a provision
25
of this Act in relation to which a Code of
Practice was in effect at the time of the
alleged contravention--
(a) the Code of Practice is admissible in
evidence in that proceeding; and
30
45
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 46
(b) if the court is satisfied in relation to any
matter which it is necessary for the
prosecution to prove in order to
establish the alleged contravention
that--
5
(i) a provision of the Code of Practice
is relevant to that matter; and
(ii) the person failed at any material
time to observe that provision--
that matter must be taken as proved
10
unless the court is satisfied that in
respect of that matter the person
complied with the provision of this Act
otherwise than by way of observance of
that provision of the Code of Practice.".
15
46. Division 1 of Part 9
After the heading to Part 9 of the Principal Act
insert--
"Division 1--Employment of Inspectors".
47. Delegation
20
For section 91(b) of the Principal Act
substitute--
"(b) delegate any power of an inspector to--
(i) any person employed under Part 3 of
the Public Administration Act 2004;
25
or
(ii) any employee of Parks Victoria
established under the Parks Victoria
Act 1998--".
46
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 48
48. New section 92 substituted
For section 92 of the Principal Act substitute--
"92. Identity cards
(1) The Department Head must issue an identity
card to each inspector containing a
5
photograph of the inspector and his or her
signature.
(2) An inspector must produce his or her identity
card for inspection if asked to do so when
performing a function or exercising a power
10
under this Act or the regulations.
(3) If a person to whom an identity card has
been issued ceases to be an inspector, the
person must return the identity card to the
Department Head as soon as practicable.".
15
49. New Divisions 2 to 11 inserted and substituted for
section 93
For section 93 of the Principal Act substitute--
'Division 2--Performance of functions or
exercise of powers
20
93. Inspectors subject to Department Head's
directions
(1) An inspector is subject to the Department
Head's directions in the performance of his
or her functions or in the exercise of his or
25
her powers under this Act or the regulations.
(2) A direction under sub-section (1) may be of
a general nature or may relate to a specified
matter or specified class of matter.
47
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 49
Division 3--Powers relating to entry
94. Power to enter
(1) An inspector may enter a place that the
inspector reasonably believes is a worksite at
any time during working hours.
5
(2) However, an inspector may enter any place
that the inspector reasonably believes is a
worksite at any time if the inspector
reasonably believes that there is an
immediate risk to the environment arising
10
from the conduct of an undertaking at the
place.
95. General powers on entry
An inspector who enters a place under this
Division may do any of the following--
15
(a) inspect, examine and make enquiries at
the place;
(b) inspect and examine any thing
(including a document) at the place;
(c) bring any equipment or materials to the
20
place that may be required;
(d) seize any thing (including a document)
at the place that may afford evidence of
the commission of an offence against
this Act or the regulations;
25
(e) seize any thing at the place for further
examination or testing but only if the
inspector reasonably believes that the
examination or testing is reasonably
necessary and cannot be reasonably
30
conducted on site;
(f) take photographs or measurements or
make sketches or recordings;
48
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 49
(g) exercise any other power conferred on
the inspector by this Act or the
regulations;
(h) do any other thing that is reasonably
necessary for the purpose of the
5
inspector performing his or her
functions or exercising his or her
powers under this Act or the
regulations.
10 Note: The powers conferred by this section are
limited if all or part of the place is used only
for residential purposes (see section 95I).
95A. Power to require production of
documents etc.
(1) An inspector who enters a place under this
15
Division may--
(a) require a person to produce a document
or part of a document located at the
place that is in the person's possession
or control; and
20
(b) examine that document or part; and
(c) require a person at the place to answer
any questions put by the inspector.
(2) A person must not, without reasonable
excuse, refuse or fail to comply with a
25
requirement under sub-section (1).
Penalty: In the case of a corporation,
300 penalty units;
In any other case 60 penalty units.
(3) Before requiring a person to produce a
30
document or part of a document or to answer
questions under sub-section (1), an
inspector--
49
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 49
(a) must produce his or her identity card
for inspection by the person and warn
the person that a refusal or failure to
comply with the requirement, without
reasonable excuse, is an offence; and
5
(b) must inform the person that he or she
may refuse or fail to answer any
question if answering the question
would tend to incriminate him or her.
(4) A person is not liable to be prosecuted for an
10
offence against sub-section (2) if the
inspector concerned failed to comply with
sub-section (3).
Note 1: The powers conferred by this section are
15 limited if all or part of the place is used only
for residential purposes (see section 95I).
Note 2: This section does not affect legal professional
privilege (see section 95T) or, in the case of a
requirement to answer questions, the privilege
20 against self-incrimination (see section 95S).
95B. Power to take samples
(1) An inspector who enters a place under this
Division may take (without payment)
samples of any thing at the place that may be
required for analysis.
25
(2) If an inspector intends to take a sample, he or
she must notify the occupier or apparent
occupier for the time being of the place of
his or her intention.
(3) Unless it is unsafe to do so, after taking the
30
sample the inspector must--
(a) divide it into as many parts as are
necessary and mark and seal or fasten
up each part in a way that the nature of
the sample allows; and
35
50
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 49
(b) if the occupier or apparent occupier
requires the inspector to give them a
part, give one part to that person; and
(c) keep one part for future comparison.
(4) If it is determined that the sample is to be
5
analysed the inspector must submit another
part to an analyst for that purpose.
Division 4--Procedure relating to entry
95C. Announcement on entry
(1) Immediately on entering a place under
10
Division 3, an inspector must take all
reasonable steps to notify the occupier or
apparent occupier for the time being of the
place of the entry and to produce his or her
identity card for inspection by that person.
15
(2) However, an inspector is not required to
notify, or produce his or her identity card for
inspection by, a person if--
(a) to do so would defeat the purpose for
which the place was entered or cause
20
unreasonable delay; or
(b) the person is already aware that the
inspector has entered the place or was
notified in advance of when he or she
would enter.
25
95D. Report to be given about entry
(1) An inspector who enters a place under
Division 3 must give a report concerning the
entry when, or as soon as practicable after,
the inspector leaves the place to the occupier
30
or apparent occupier for the time being of the
place.
51
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 49
(2) The report must be in writing and include--
(a) the time of the entry and departure; and
(b) the purpose of the entry; and
(c) a description of things done while at the
place; and
5
(d) a summary of the inspector's
observations while at the place; and
(e) the procedure for contacting the
Department Head and the inspector for
further details of the entry; and
10
(f) the procedure for seeking review of any
decision made by the inspector during
the entry.
(3) If the inspector takes photographs or makes
sketches or recordings under section 95(f),
15
the report must also include a statement
that--
(a) the photographs have been taken or
sketches or recordings have been made;
and
20
(b) they are or will be available for
inspection at a specified place.
(4) A report under this section may be combined
with a report given by the inspector under
section 103 of the Occupational Health and
25
Safety Act 2004 in respect of that place.
Division 5--Search warrants
95E. Definition
In this Division a "place" includes a
worksite, premises and a vehicle.
30
52
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 49
95F. Issue of search warrants
(1) An inspector may apply to a magistrate for
the issue of a search warrant in relation to a
particular place if the inspector believes on
reasonable grounds that there is, or may be
5
within the next 72 hours, a particular thing
(including a document) at the place that may
afford evidence of the commission of an
offence against this Act or the regulations.
(2) A magistrate may issue the search warrant if
10
he or she is satisfied by evidence on oath,
whether oral or by affidavit, that there are
reasonable grounds for suspecting that there
is, or may be within 72 hours, a particular
thing (including a document) at the place that
15
may afford evidence of the commission of an
offence against this Act or the regulations.
(3) The search warrant may authorise a named
inspector and any assistants the inspector
considers necessary--
20
(a) to enter the place or part of the place
named or described in the warrant; and
(b) to search for the thing named or
described in the warrant.
(4) In addition to any other requirement, the
25
search warrant must state--
(a) the offence suspected; and
(b) the place to be searched; and
(c) a description of the thing for which the
search is to be made; and
30
(d) any conditions to which the warrant is
subject; and
53
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 49
(e) whether entry is authorised to be made
at any time or during specified hours;
and
(f) that the warrant authorises entry on
only one occasion; and
5
(g) a day, not later than 7 days after the
warrant is issued, on which it ceases to
have effect.
(5) A search warrant must be issued in
accordance with the Magistrates' Court Act
10
1989 and in the form prescribed under that
Act.
(6) The rules that apply to search warrants
mentioned in the Magistrates' Court Act
1989 extend and apply to search warrants
15
under this section.
95G. Announcement before entry on warrant
(1) Before executing a search warrant, the
inspector named in the warrant or an
assistant to the inspector must--
20
(a) announce that he or she is authorised by
the warrant to enter the place; and
(b) give any person at the place an
opportunity to allow that entry.
(2) However, the inspector or an assistant to the
25
inspector need not comply with sub-
section (1) if he or she believes on
reasonable grounds that immediate entry to
the place is needed to ensure that the
effective execution of the warrant is not
30
frustrated.
54
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 49
95H. Copy of warrant to be given to occupier
If an occupier or apparent occupier is present
at the place when a search warrant is being
executed, the inspector must--
(a) identify himself or herself to that
5
person by producing his or her identity
card for inspection; and
(b) give that person a copy of the execution
copy of the warrant.
Division 6--Limitation on entry powers
10
95I. Places used for residential purposes
Despite anything else in this Part, the powers
of an inspector under this Part in relation to
entering a place are not exercisable in respect
of any part of a place that is used only for
15
residential purposes except--
(a) with the consent of the occupier for the
time being of the place; or
(b) under the authority conferred by a
search warrant.
20
Division 7--Return and forfeiture of seized
things
95J. Return of seized things
(1) As soon as possible after an inspector seizes
any thing (including a document) under this
25
Part the Department Head must return the
thing to the owner unless--
55
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 49
(a) the Department Head considers it
necessary to retain the thing because it
may afford evidence in proceedings,
that have been or may be commenced,
for an offence against this Act or the
5
regulations; or
(b) the thing is forfeited to the Crown
under section 95K; or
(c) the Department Head is otherwise
authorised (by a law or court order) to
10
retain, destroy or dispose of the thing.
(2) The thing may be returned either
unconditionally or on such terms and
conditions as the Department Head considers
appropriate.
15
(3) If the Department Head imposes terms or
conditions on the return of a thing, the owner
must comply with each of those terms and
conditions.
Penalty: In the case of a corporation,
20
300 penalty units;
In any other case 60 penalty units.
95K. Forfeiture of seized things
Any thing (including a document) that an
inspector has seized and retained under this
25
Part is forfeited to the Crown if the
Department Head--
(a) cannot find its owner despite making
reasonable enquiries; or
(b) cannot return it to the owner despite
30
making reasonable efforts.
56
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 49
Division 8--Other powers
95L. Power to require name and address
(1) An inspector may ask a person to state his or
her name and address if the inspector
reasonably believes that the person--
5
(a) may be able to assist in the
investigation of an offence under this
Act that has been committed or is
suspected of having been committed; or
(b) has committed or is about to commit an
10
offence under this Act or the
regulations.
(2) The inspector must inform the person of the
grounds for his or her belief in sufficient
detail to allow the person to understand the
15
nature of the offence or suspected offence.
(3) A person who, in response to being asked to
state his or her name and address in
accordance with this section--
(a) refuses or fails to do so; or
20
(b) states a name that is false in a material
particular; or
(c) states an address other than the full and
correct address of his or her ordinary
place of residence or business--
25
is guilty of an offence and liable to a fine not
exceeding 5 penalty units.
(4) A person who is asked to state his or her
name and address may ask the inspector to
produce his or her identity card for
30
inspection.
57
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 49
95M. Power to give directions
(1) An inspector may give a direction (either
orally or in writing) to a person at a worksite
if the inspector reasonably believes that it is
necessary to do so because of an immediate
5
risk to the environment.
(2) A person must not, without reasonable
excuse, refuse or fail to comply with a
direction given to the person under sub-
section (1).
10
Penalty: In the case of a corporation,
500 penalty units;
In any other case 100 penalty
units.
Division 9--Other matters
15
95N. Occupier must assist inspector
The occupier or apparent occupier for the
time being of a worksite must not, without
reasonable excuse, refuse or fail to provide
such assistance as an inspector may
20
reasonably require for the performance of his
or her functions or exercise of his or her
powers under this Act or the regulations.
Penalty: In the case of a corporation,
300 penalty units;
25
In any other case 60 penalty units.
95O. Other assistance in exercising powers
(1) For the purpose of exercising a power under
this Act or the regulations, an inspector may
seek the assistance of any person.
30
58
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 49
(2) If the power being exercised involves entry
to a worksite, the occupier or apparent
occupier for the time being of the worksite
must allow the person assisting access to that
worksite.
5
Penalty: In the case of a corporation,
300 penalty units;
In any other case 60 penalty units.
(3) If an inspector uses the assistance of an
interpreter--
10
(a) any enquiry or request made by the
interpreter on the inspector's behalf is
taken to have been made by the
inspector; and
(b) any answer given to the interpreter is
15
taken to have been given to the
inspector.
95P. Inspector may take affidavits
An inspector is authorised to take affidavits
for any purpose relating or incidental to the
20
performance of his or her functions or
exercise of his or her powers under this Act
or the regulations.
95Q. Inspector may copy documents
An inspector may make copies of, or take
25
extracts from, a document or part of a
document given to the inspector in
accordance with a requirement under this
Act or the regulations.
59
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 49
Division 10--Offences
95R. Offences in relation to inspections
(1) A person must not wilfully assault, obstruct
or attempt to obstruct, threaten, intimidate or
attempt to intimidate an inspector in the
5
exercise of the inspector's powers or the
discharge of the inspector's duties.
Penalty: In the case of a corporation,
1000 penalty units;
In any other case, 200 penalty
10
units.
(2) A person must not--
(a) contravene or fail to comply with any
lawful requirement of an inspector; or
(b) make to an inspector exercising a
15
power or discharging a duty under this
Act a statement knowing it to be false
or misleading in any particular.
Penalty: In the case of a corporation,
500 penalty units;
20
In any other case, 100 penalty
units.
(3) A reference in this section to an inspector
includes a reference to a person acting under
an instrument of delegation under
25
section 91(b).
60
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 50
Division 11--Protection of privileges
95S. Protection against self-incrimination
(1) A natural person may refuse or fail to give
information or do any other thing that the
person is required to do by or under this Part
5
if giving the information or doing the other
thing would tend to incriminate the person.
(2) However, sub-section (1) does not apply
to--
(a) the production of a document or part of
10
a document that the person is required
by this Part to produce; or
(b) the giving of a person's name or address
in accordance with section 95L.
95T. Legal professional privilege not affected
15
Nothing in this Act or the regulations--
(a) entitles or requires a person to disclose
information that is the subject of legal
professional privilege; or
(b) affects the law or practice relating to
20
legal professional privilege.'.
50. New section 105 inserted
After section 104 of the Principal Act insert--
"105. Annual report
(1) A mining warden must, within 3 months
25
after the end of a financial year, submit a
report to the Minister.
(2) A report under sub-section (1) must include a
brief summary of the following things that
occurred in that financial year--
30
61
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 51
(a) the nature and status of any dispute
referred to the mining warden under
section 97;
(b) the nature and status of any matter
referred to the mining warden under
5
section 98;
(c) any other activity commenced,
conducted or completed by the mining
warden under this Act.".
51. Order to cease work
10
(1) For section 110(1) of the Principal Act
substitute--
"(1) This section applies if the Minister believes
on reasonable grounds that--
(a) an act or omission by the holder of an
15
authority is likely to result in a risk to
the environment; or
(b) the holder of an authority--
(i) has contravened or is likely to
contravene this Act or the
20
regulations; or
(ii) has not complied with any
condition to which the authority is
subject or any condition specified
under section 44; or
25
(iii) has not complied with any
relevant planning scheme or
permit; or
(iv) has not complied with any
condition applying to the carrying
30
out of the work plan under the
authority; or
62
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 52
(v) has undertaken work on land
otherwise than in accordance with
the work plan under the authority;
or
(c) a former licensee has failed to comply
5
with section 81.".
(2) After section 110(7) of the Principal Act insert--
"(8) In sub-sections (2) to (6) a reference to the
holder of an authority or a licensee includes
a reference to a former licensee.".
10
52. New section 110A inserted
After section 110 of the Principal Act insert--
'110A. Enforcement order
(1) An inspector who believes on reasonable
grounds that a person (other than the holder
15
of an authority) is carrying out or is likely to
carry out an activity on land in contravention
of this Act or the regulations may issue a
notice to the person--
(a) to stop that activity; and
20
(b) to take within a specified period any
action necessary to remedy the
contravention.
(2) A person must not, without reasonable
excuse, fail to comply with a notice under
25
this section.
Penalty: In the case of a corporation,
1000 penalty units;
In any other case, 200 penalty
units.
30
(3) In this section "authority" has the same
meaning as it has in section 110.'.
63
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 53
53. New section 120A inserted
After section 120 of the Principal Act insert--
"120A. Ministerial guidelines
(1) The Minister may, from time to time, issue
guidelines relating to any of the objectives or
5
purposes of this Act or the regulations made
under this Act.
(2) A guideline has no effect until a notice of its
making has been published in the
Government Gazette.
10
(3) The guidelines must be made available for
public inspection free of charge--
(a) at the principal office of the
Department and major regional offices
of the Department; or
15
(b) in electronic form published on the
Department's Internet site.".
54. Regulations
Section 124(1)(o) of the Principal Act is repealed.
55. New sections 133 and 134 inserted
20
After section 132 of the Principal Act insert--
'133. Validation of certain exploration and
mining work--2006 amendments
(1) Despite section 45 (as in force immediately
before the commencement date), a licensee
25
who, before the commencement date, did
any work under the licence within an area of
land prohibited by section 45(1)(a)(i) to (x)
(as in force immediately before the
commencement date) or within 100 metres
30
below that area is deemed always to have
complied with section 45 in respect of that
work if--
64
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 55
(a) at the time the work was done an
approved work plan and, in the case of
a mining licence, a work authority, was
registered in respect of the licence; and
(b) the work was done in accordance with
5
the approved work plan.
(2) Nothing in sub-section (1) affects the rights
of the parties in the proceedings in VCAT
known as Tech-Sol Resources Pty Ltd v
Minister for Energy Industries and
10
Resources [2004] VCAT 1648 and [2004]
VCAT 1654.
(3) In this section "commencement date"
means the date of commencement of
section 34 of the Mineral Resources
15
Development (Sustainable Development)
Act 2006.
134. Change of title provision--2006
amendments
On the commencement of section 4 of the
20
Mineral Resources Development
(Sustainable Development) Act 2006, in
any Act (other than this Act) or in any
instrument made under any Act or in any
other document of any kind, any reference to
25
the Mineral Resources Development Act
1990 is deemed to be a reference to the
Mineral Resources (Sustainable
Development) Act 1990 so far as it applies
to any period on or after that
30
commencement, unless the contrary intention
appears.'.
65
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 2--Amendments to the Mineral Resources Development Act 1990
s. 56
56. New section 135 inserted
At the end of Part 14 insert--
"135. Transitional provision--2006
amendments
A person who held a licence immediately
5
before the commencement of section 26(2)
of the Mineral Resources Development
(Sustainable Development) Act 2006 is not
required to provide a community
engagement plan in accordance with section
10
40(3)(b)(ii) as part of the work plan for that
licence if the person before that
commencement had lodged a work plan
under section 40 and the work plan had not
been approved.
15
Note: A licensee who is not required under
section 135 to provide a community
engagement plan under section 40 as part of
the initial work plan may be required to
20 provide a community engagement plan when
the work plan is subsequently varied or the
licence is renewed.".
57. Amendment of Schedule 1
In item 24 in Schedule 1 to the Principal Act, in
proposed section 32(2)(j) of the Sale of Land Act
25
1962, for "Mineral Resources Development Act
1990" substitute "Mineral Resources
(Sustainable Development) Act 1990".
58. Amendment of Schedule 3
In clause 5 of Schedule 3 to the Principal Act, for
30
"Ministers administering the Crown Land
(Reserves) Act 1978 and the Forests Act 1958"
substitute "Crown land Minister".
__________________
66
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 3--Amendments to Other Acts
s. 59
PART 3--AMENDMENTS TO OTHER ACTS
See:
Division 1--Amendments to the Environment Protection Act No.
8056.
Act 1970 Reprint No. 15
as at
59. Appointment of environmental auditor 12 December
2005
and
(1) After section 53S(2) of the Environment
5 amending
Protection Act 1970 insert-- Act Nos
62/2005,
"(2A) The Authority in appointing an 99/2005 and
32/2006.
environmental auditor, or in suspending or LawToday:
revoking, or imposing conditions on, such an www.dms.
dpc.vic.
appointment, must have regard to any
10 gov.au
relevant guidelines issued under sub-
section (6).".
(2) In section 53S(5) of the Environment Protection
Act 1970--
(a) in paragraph (c), for "statements of
15
environmental audit." substitute "statements
of environmental audit; and";
(b) after paragraph (c) insert--
"(d) any function conferred on an
environmental auditor under this or any
20
other Act.".
(3) In section 53S(6) of the Environment Protection
Act 1970 for "functions" substitute "functions
under this or any other Act.".
60. Offences
25
In 53ZC(1) of the Environment Protection Act
1970--
(a) in paragraph (a), after "Authority" insert
"or to any other person in carrying out a
function under this or any other Act";
30
67
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Part 3--Amendments to Other Acts
s. 61
(b) after paragraph (b) insert--
"(ba) issue a certificate or any other
document which is false or misleading
in carrying out a function under any
other Act; or";
5
(c) in paragraph (c), after "Authority" insert
"or from any other person in carrying out a
function under this or any other Act".
Division 2--Amendments to Other Acts
61. Consequential amendments
10
On the coming into operation of an item in the
Schedule, the Act referred to in the heading to that
item is amended as set out in that item.
__________________
68
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Sch.
SCHEDULE
Section 61
CONSEQUENTIAL AMENDMENTS TO OTHER ACTS
1. Aboriginal Heritage Act 2006
5 1.1 In section 50, in paragraph (a) of the definition of "earth
resource authorisation", for "Mineral Resources
Development Act 1990" substitute "Mineral Resources
(Sustainable Development) Act 1990".
1.2 In section 50, in paragraph (a) of the definition of "earth
10 resource law", for "Mineral Resources Development Act
1990" substitute "Mineral Resources (Sustainable
Development) Act 1990".
1.3 For the heading to item 5 in Schedule 2 substitute--
"Mineral Resources (Sustainable Development) Act
15 1990".
1.4 In item 5(4) in Schedule 2, in proposed section 18(b) of the
Mineral Resources (Sustainable Development) Act 1990,
for "relates." substitute "relates; and".
2. Aboriginal Land (Manatunga Land) Act 1992
20 In section 3(2)(b), for "Mineral Resources Development
Act 1990" substitute "Mineral Resources (Sustainable
Development) Act 1990".
3. Aboriginal Land (Northcote Land) Act 1989
In section 5(4), for "Mineral Resources Development Act
25 1990" substitute "Mineral Resources (Sustainable
Development) Act 1990".
4. Aboriginal Lands (Aborigines' Advancement League) (Watt
Street, Northcote) Act 1982
In section 3(4), for "Mineral Resources Development Act
30 1990" substitute "Mineral Resources (Sustainable
Development) Act 1990".
69
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Sch.
5. Catchment and Land Protection Act 1994
5.1 In section 3, in the definition of "land", for "Mineral
Resources Development Act 1990" substitute "Mineral
Resources (Sustainable Development) Act 1990".
5 5.2 In sections 33(4)(a), 33(4)(c), 50(c) and 93(1), for "Mineral
Resources Development Act 1990" (wherever occurring)
substitute "Mineral Resources (Sustainable
Development) Act 1990".
6. Coroners Act 1985
10 In section 45(4)(f), for "Mineral Resources Development
Act 1990" substitute "Mineral Resources (Sustainable
Development) Act 1990".
7. Crown Land (Reserves) Act 1978
In sections 7(1) and 7(3), for "Mineral Resources
15 Development Act 1990" (wherever occurring) substitute
"Mineral Resources (Sustainable Development) Act
1990".
8. Dangerous Goods Act 1985
In sections 10B(2)(b), 11(2)(a) and 37(4), for "Mineral
20 Resources Development Act 1990" (wherever occurring)
substitute "Mineral Resources (Sustainable
Development) Act 1990".
9. EastLink Project Act 2004
In section 131(1), for "Mineral Resources Development
25 Act 1990" substitute "Mineral Resources (Sustainable
Development) Act 1990".
10. Electricity Industry Act 2000
In sections 87(1), 87(2)(b) and 87(3), for "Mineral
Resources Development Act 1990" (wherever occurring)
30 substitute "Mineral Resources (Sustainable
Development) Act 1990".
11. Environment Protection Act 1970
In sections 19B(3)(a)(iv) and 19B(4C), for "Mineral
Resources Development Act 1990" (wherever occurring)
35 substitute "Mineral Resources (Sustainable
Development) Act 1990".
70
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Sch.
12. Equipment (Public Safety) Act 1994
In section 5(c)(ii), for "Mineral Resources Development
Act 1990" substitute "Mineral Resources (Sustainable
Development) Act 1990".
5 13. Extractive Industries Development Act 1995
In sections 1(c), 26(1)(b), 26(3), 27(1) and 27(2), for
"Mineral Resources Development Act 1990" (wherever
occurring) substitute "Mineral Resources (Sustainable
Development) Act 1990".
10 14. Fences Act 1968
In section 3, in the definition of "occupier", for "Mineral
Resources Development Act 1990" (where twice
occurring) substitute "Mineral Resources (Sustainable
Development) Act 1990".
15 15. Flora and Fauna Guarantee Act 1988
In section 37(b), for "Mineral Resources Development
Act 1990" substitute "Mineral Resources (Sustainable
Development) Act 1990".
16. Forests Act 1958
20 In sections 6, 7, 42(4), 45(2), 49(1) and 50(5A), for
"Mineral Resources Development Act 1990" (wherever
occurring) substitute "Mineral Resources (Sustainable
Development) Act 1990".
17. Geothermal Energy Resources Act 2005
25 17.1 In section 4(1), in paragraph (c) of the definition of
"unrestricted Crown land", for "Mineral Resources
Development Act 1990" substitute "Mineral Resources
(Sustainable Development) Act 1990".
17.2 In section 81, for "Mineral Resources Development Act
30 1990" substitute "Mineral Resources (Sustainable
Development) Act 1990".
18. Land Acquisition and Compensation Act 1986
In sections 38(1) and 38(3), for "Mineral Resources
Development Act 1990" (wherever occurring) substitute
35 "Mineral Resources (Sustainable Development) Act
1990".
71
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Sch.
19. Land Act 1958
In sections 2(3), 171, 190, 204, 205(2), 212(1), 217 and 340,
for "Mineral Resources Development Act 1990"
(wherever occurring) substitute "Mineral Resources
5 (Sustainable Development) Act 1990".
20. Land Tax Act 2005
In section 86(3), in paragraph (a) of the definition of "mine",
for "Mineral Resources Development Act 1990"
substitute "Mineral Resources (Sustainable
10 Development) Act 1990".
21. Melbourne City Link Act 1995
21.1 In section 20F(1)(d), for "Mineral Resources
Development Act 1990" substitute "Mineral Resources
(Sustainable Development) Act 1990".
15 21.2 In section 64(1)(e), for "Mineral Resources Development
Act 1991" substitute "Mineral Resources (Sustainable
Development) Act 1990".
22. Mines (Aluminium Agreement) (Brown Coal Royalties)
Act 2005
20 In section 3, in proposed section 11(3) of the Mines
(Aluminium Agreement) Act 1961, for "Mineral
Resources Development Act 1990" substitute "Mineral
Resources (Sustainable Development) Act 1990".
23. National Parks Act 1975
25 23.1 In section 3(1), in the definitions of "exploration licence",
"miner's right", "mining licence", "search" and "tourist
fossicking authority", for "Mineral Resources
Development Act 1990" (wherever occurring) substitute
"Mineral Resources (Sustainable Development) Act
30 1990".
23.2 In section 40, for "Mineral Resources Development Act
1990" (wherever occurring) substitute "Mineral
Resources (Sustainable Development) Act 1990".
24. National Parks (Additions and Other Amendments) Act 2004
35 In section 33, in proposed section 49A of the Crown Land
(Reserves) Act 1978, for "Mineral Resources
Development Act 1990" substitute "Mineral Resources
(Sustainable Development) Act 1990".
72
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Sch.
25. Nuclear Activities (Prohibitions) Act 1983
25.1 In section 2, in the definition of "mining title", for "Mineral
Resources Development Act 1990" substitute "Mineral
Resources (Sustainable Development) Act 1990".
5 25.2 In section 9(1)(i), for "Mineral Resources Development
Act 1990" substitute "Mineral Resources (Sustainable
Development) Act 1990".
26. Occupational Health and Safety Act 2004
26.1 In section 37(4), in paragraph (a) of the definition of "mine",
10 for "Mineral Resources Development Act 1990"
substitute "Mineral Resources (Sustainable
Development) Act 1990".
26.2 In section 95(1)(b), for "Mineral Resources Development
Act 1990" substitute "Mineral Resources (Sustainable
15 Development) Act 1990".
27. Petroleum Act 1998
In section 4, in the definition of "restricted Crown land" for
"Mineral Resources Development Act 1990" substitute
"Mineral Resources (Sustainable Development) Act
20 1990".
28. Safety on Public Land Act 2004
In section 16, for "Mineral Resources Development Act
1990" substitute "Mineral Resources (Sustainable
Development) Act 1990".
25 29. Summary Offences Act 1966
In section 50(4), for "Mineral Resources Development
Act 1990" substitute "Mineral Resources (Sustainable
Development) Act 1990".
30. Transfer of Land Act 1958
30 In section 4(1), in the definition of "land", for "Mineral
Resources Development Act 1990" substitute "Mineral
Resources (Sustainable Development) Act 1990".
31. Underseas Mineral Resources Act 1963
In section 2, for "Mineral Resources Development Act
35 1990" (wherever occurring) substitute "Mineral
Resources (Sustainable Development) Act 1990".
73
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Sch.
32. Victorian Civil and Administrative Tribunal Act 1998
32.1 In the heading to Part 15 of Schedule 1, for "MINERAL
RESOURCES DEVELOPMENT ACT 1990" substitute
"MINERAL RESOURCES (SUSTAINABLE
5 DEVELOPMENT) ACT 1990".
32.2 In clause 51 of Schedule 1, for "Mineral Resources
Development Act 1990" substitute "Mineral Resources
(Sustainable Development) Act 1990".
33. Victorian Plantations Corporation Act 1993
10 33.1 In section 3, in the definition of "forest produce", for
"Mineral Resources Development Act 1990" substitute
"Mineral Resources (Sustainable Development) Act
1990".
33.2 In sections 9(2)(b) and 26(1), for "Mineral Resources
15 Development Act 1990" (wherever occurring) substitute
"Mineral Resources (Sustainable Development) Act
1990".
34. Wildlife Act 1975
In section 19(1) for "Mineral Resources Development Act
20 1990" (where twice occurring) substitute "Mineral
Resources (Sustainable Development) Act 1990".
74
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
Mineral Resources Development (Sustainable Development) Act
2006
Act No.
Endnotes
ENDNOTES
By Authority. Government Printer for the State of Victoria.
75
551440B.I1-19/7/2006 BILL LA INTRODUCTION 19/7/2006
[Index] [Search] [Download] [Related Items] [Help]