(1)  An application for a licence is pending from the day on which it is lodged until whichever of the following happens first:
(a) the application is granted;
(b) the application is refused;
(c) the application lapses;
(d) the application is withdrawn.
(2)  An application for a licence lapses –
(a) 12 months after it is lodged, if it is not determined or withdrawn by that time; or
(b) at a later date fixed by the Director if –
(i) the failure to determine the application was not caused by a default of the applicant; or
(ii) there is, in the opinion of the Director, a sufficient reason for fixing a later date.