South Australian Consolidated Acts74BC—Content of fortification removal order
(1) A fortification
removal order must include—
(a) a
statement to the effect that specified fortifications at the premises must be
removed or modified, as directed by the Court, within a period of time fixed
by the order (which may not be less than 14 days after service of the order);
and
(b)
subject to subsection (2)—a statement of the grounds on which the
order has been issued; and
(c) an
explanation of the right of objection under section 74BE; and
(d) an
explanation of the Commissioner's power to enforce the order under
section 74BI.
(2) A statement of the
grounds on which a fortification removal order has been issued must not
contain information in respect of which an order has been made by the Court
under section 74BB(5).
(3) A copy of the
affidavit verifying the grounds on which the application was made must be
attached to the fortification removal order unless disclosure of information
included in the affidavit would be in breach of an order of the Court under
section 74BB(5).
(4) If disclosure of
information included in the affidavit would be in breach of an order of the
Court under section section 74BB(5), an edited copy of the
affidavit, from which the information that cannot be disclosed has been
removed or erased, may be attached to the fortification removal order.