WATER SUPPLY (SAFETY AND RELIABILITY) ACT 2008 - SECT 352K
Approval of plan
WATER SUPPLY (SAFETY AND RELIABILITY) ACT 2008 - SECT 352K
Approval of plan
352K Approval of plan
(1) If the chief executive approves the emergency action plan, the chief
executive must—
(a) give notice of the approval to the owner of the dam; and
(b) give a copy of the approved plan to the emergency management chief
executive; and
(c) publish the approved plan in the register of approved
emergency action plans under section 352M.
(2) The approval must be for a
period of no more than 5 years stated in the approved plan.
(3) Subsection
(4) applies if, within 30 business days after the emergency action plan is
given to the chief executive for approval under section 352For 352S, the
chief executive has not decided to approve, or refuse to approve, the plan.
(4) The chief executive is taken to have approved the plan on the day that is
30 business days after the plan was given to the chief executive (the
"deemed approval day" ).
(5) If subsection (4) applies to an emergency action
plan—