WATER SUPPLY (SAFETY AND RELIABILITY) ACT 2008 - SECT 349
Decision about failure impact assessment
WATER SUPPLY (SAFETY AND RELIABILITY) ACT 2008 - SECT 349
Decision about failure impact assessment
349 Decision about failure impact assessment
(1) The chief executive may decide to accept, reject or require a review of a
failure impact assessment.
(2) However, before requiring a review of, or
rejecting, the assessment, the chief executive may require the owner to give
additional information about the assessment to assist the chief executive in
deciding if the review or rejection is necessary.
(3) Without limiting
subsection (2) , the chief executive may require the preparation of documents
including a comprehensive report, by a registered professional engineer, on
the design and operation of the dam.