259 Changing plan after review
(1) This section applies if a review of a recycled water management plan
indicates the plan should be changed to be consistent with—
(a) the
operation of the recycled water scheme to which it relates; or
(b) the water
quality criteria for recycled water relevant to the scheme; or
(c) best
practice industry standards for the production and supply of recycled water.
(2) If the recycled water scheme is a single-entity recycled water scheme, the
recycled water provider for the scheme must, within 60 business days after the
review ends—
(a) amend the recycled water management plan for the scheme to
be consistent with the matters mentioned in subsection (1) ; and
(b) apply to
the regulator for approval of the amended plan.
Penalty—
Maximum
penalty—200 penalty units.
(3) If the recycled water scheme is a
multiple-entity recycled water scheme—
(a) the scheme manager for the scheme
must, within 60 business days after the review ends, amend the manager’s
scheme manager plan for the scheme to the extent necessary to be consistent
with the matters mentioned in subsection (1) ; and
(b) each declared entity
for the scheme must, within 60 business days after the review ends, amend the
entity’s scheme provider plan for the scheme to the extent necessary to be
consistent with the matters mentioned in subsection (1) .
Penalty—
Maximum penalty—200 penalty units.
(4) If a scheme manager plan or scheme
provider plan for a multiple-entity recycled water scheme is amended under
subsection (3) , the scheme manager for the scheme must as soon as practicable
apply to the regulator for approval of the amended recycled water management
plan for the scheme.
Penalty—
Maximum penalty—200 penalty units.
(5) An amended recycled water management plan must indicate the way the plan
has been amended to be consistent with the matters mentioned in subsection (1)
.
(6) Sections 202(2) , (3) and (4) , and 203 to 208 apply to an application
under this section—
(a) as if a reference in the sections to the recycled
water management plan were a reference to the amended recycled water
management plan; and
(b) as if a reference in the sections to the plan were a
reference to the amended plan.