WATER SUPPLY (SAFETY AND RELIABILITY) ACT 2008 - SECT 259 Changing plan after review

WATER SUPPLY (SAFETY AND RELIABILITY) ACT 2008 - SECT 259

Changing plan after review

259 Changing plan after review

(1) This section applies if a review of a recycled water management plan indicates the plan should be changed to be consistent with—
(a) the operation of the recycled water scheme to which it relates; or
(b) the water quality criteria for recycled water relevant to the scheme; or
(c) best practice industry standards for the production and supply of recycled water.
(2) If the recycled water scheme is a single-entity recycled water scheme, the recycled water provider for the scheme must, within 60 business days after the review ends—
(a) amend the recycled water management plan for the scheme to be consistent with the matters mentioned in subsection (1) ; and
(b) apply to the regulator for approval of the amended plan.
Penalty—
Maximum penalty—200 penalty units.
(3) If the recycled water scheme is a multiple-entity recycled water scheme—
(a) the scheme manager for the scheme must, within 60 business days after the review ends, amend the manager’s scheme manager plan for the scheme to the extent necessary to be consistent with the matters mentioned in subsection (1) ; and
(b) each declared entity for the scheme must, within 60 business days after the review ends, amend the entity’s scheme provider plan for the scheme to the extent necessary to be consistent with the matters mentioned in subsection (1) .
Penalty—
Maximum penalty—200 penalty units.
(4) If a scheme manager plan or scheme provider plan for a multiple-entity recycled water scheme is amended under subsection (3) , the scheme manager for the scheme must as soon as practicable apply to the regulator for approval of the amended recycled water management plan for the scheme.
Penalty—
Maximum penalty—200 penalty units.
(5) An amended recycled water management plan must indicate the way the plan has been amended to be consistent with the matters mentioned in subsection (1) .
(6) Sections 202 (2) , (3) and (4) , and 203 to 208 apply to an application under this section—
(a) as if a reference in the sections to the recycled water management plan were a reference to the amended recycled water management plan; and
(b) as if a reference in the sections to the plan were a reference to the amended plan.