WATER ACT 2000 - SECT 399
Approval of baseline assessment plan
WATER ACT 2000 - SECT 399
Approval of baseline assessment plan
399 Approval of baseline assessment plan
(1) If a baseline assessment plan is given to the chief executive under
section 397 , the chief executive must— (a) approve the plan, with or
without conditions; or
(b) ask the holder to amend the plan and submit the
amended plan within a stated reasonable period.
(1A) The holder must submit
the amended plan to the chief executive within the stated reasonable period.
Penalty— Maximum penalty—50 penalty units.
(2) The chief executive
must give notice of the decision to the resource tenure holder within 10
business days after making the decision.
(3) If the chief executive approves
the plan, the plan takes effect on the day stated in the notice.