WATER ACT 2000 - SECT 386
Publishing approval and making report available
WATER ACT 2000 - SECT 386
Publishing approval and making report available
386 Publishing approval and making report available
(1) The responsible entity that gave the chief executive an underground water
impact report or final report that is approved by the chief executive must—
(a) within 10 business days after receiving notice of the approval—
(i)
publish, in the way required by the chief executive, a notice about the
approval that complies with subsection (2) ; and
(ii) give a copy of the
notice to each bore owner of a water bore within the area to which the report
relates; and
(b) within 15 business days after receiving notice of the
approval—advise the chief executive that the entity has complied with
paragraph (a) .
Penalty—
Maximum penalty—50 penalty units.
(2)
The notice must state—
(a) that copies of the approved report may be
obtained from the entity; and
(b) how the copies may be obtained.
(3) The
responsible entity must give a copy of the report to any person who requests a
copy.
(4) The chief executive must publish each approved underground water
impact report and approved final report on a Queensland Government website.