(1) This section applies if an operations manual for a resource operations
licence or distribution operations licence becomes inconsistent with the water
plan outcomes, measures and objectives mentioned in section 198(1) (a) and
(b) .
(2) The holder of the licence to which the operations manual applies
must apply to the chief executive in writing to amend the manual.
(3)
However, if the holder does not apply, the chief executive may direct the
holder to review the operations manual to address the inconsistency.
(4) If
the chief executive directs the holder to review the operations manual under
subsection (3) , the holder must review the manual as required by the chief
executive and apply to the chief executive in writing to amend it.
(5) The
provisions of this division applying to the approval and publication of an
operations manual apply—
(a) as if a reference to the approval of the manual
were a reference to its amendment; and
(b) with any necessary changes.
(6)
This section applies if an operations manual is inconsistent with a resource
operations licence or distribution operations licence.
(7) The provisions of
the licence prevail to the extent of the inconsistency.