WATER ACT 2000 - SECT 188
Additional requirements for transfer of distribution operations licence to nominee
WATER ACT 2000 - SECT 188
Additional requirements for transfer of distribution operations licence to nominee
188 Additional requirements for transfer of distribution operations licence to
nominee
(1) This section applies to an application to transfer all or part of a
distribution operations licence if—
(a) the transferee is the nominee of the
current infrastructure owner; or
(b) the current infrastructure owner is
transferring ownership of the water infrastructure to which the licence or
part applies to another entity (the
"incoming owner" ) and the transferee for the licence or part is the nominee
of the incoming owner.
(2) The application must be—
(a) accompanied by the
written consent of—
(i) the current infrastructure owner, unless the owner
is the applicant; and
(ii) if subsection (1) (b) applies—the
incoming owner; and
(b) supported by sufficient information to enable the
chief executive to decide whether or not to approve the nominee under
section 178.