34G Preparation of draft IAR
(1) The proponent of the project must prepare a draft IAR for the project.
(2) The draft IAR must include— (a) details of the project; and (b)
information about the likely environmental effects of the project; and (c) a
statement about whether or not any of the following approvals (each of which
is a
"notifiable approval" ) is required for the project— (i) a
development approval if the development application for the approval would,
under the Planning Act , require impact assessment; (ii) an
environmental authority if the application for the authority would, under the
Environmental Protection Act , chapter 5 , part 4 , require public
notification; (iii) another approval under an Act if— (A) the application
for the approval requires, other than under the Planning Act or the
Environmental Protection Act , chapter 5 , an EIS or a similar statement to
address the environmental effects of the approval ; and (B) the application
for, or the granting of, the approval requires public notification under the
relevant Act.