44A Consideration of application for permit

(1) The authority must consider the application and either grant, or refuse to grant, the application.

(2) However, before deciding the application, the authority may, by written notice given to the applicant, require the applicant to give the authority, within a reasonable period of at least 14 days stated in the notice, further information or a document the authority reasonably considers is needed to decide the application.

(3) The applicant is taken to have withdrawn the application if, within the stated period, the applicant does not comply with the requirement.

(4) The authority may extend the stated period at the request of the applicant.