Queensland Consolidated Acts(1) The authority must give notice in writing to a licensee at least 28 days before the renewal day for the licensee's licence.
(2) The notice must state the following--
(a) the renewal day for the licensee's licence;
(b) if the licensee is an individual, whether or not the authority requires 2 recent passport-size photographs of the licensee suitable for inclusion in a licence and certified in the way prescribed by regulation;
(c) the renewal fee for the licence and that it must be paid on or before the renewal day;
(d) the amount, if any, to be added to the renewal fee under section 37C;
(e) for a contractor's licence, when the documentary evidence required by the financial requirements stated in the board's policies must be given to the authority.