QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION ACT 1991 - SECT 67U
Void payment provision in construction management trade contract or subcontract
QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION ACT 1991 - SECT 67U
Void payment provision in construction management trade contract or subcontract
67U Void payment provision in construction management trade contract or
subcontract
(1) A provision in a construction management trade contract or subcontract is
void to the extent it provides for payment of a progress payment by a
contracting party to a contracted party later than 25 business days after
submission of a payment claim.
(2) In this section—
"business day" means a day that is not—
(a) a Saturday or Sunday; or
(b) a
public holiday, special holiday or bank holiday in the place in which any
relevant act is to be or may be done; or
(c) a day in the period from 22
December in a particular year to 10 January in the following year, both days
inclusive.