QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION ACT 1991 - SECT 67U Void payment provision in construction management trade contract or subcontract

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION ACT 1991 - SECT 67U

Void payment provision in construction management trade contract or subcontract

67U Void payment provision in construction management trade contract or subcontract

(1) A provision in a construction management trade contract or subcontract is void to the extent it provides for payment of a progress payment by a contracting party to a contracted party later than 25 business days after submission of a payment claim.
(2) In this section—


"business day" means a day that is not—
(a) a Saturday or Sunday; or
(b) a public holiday, special holiday or bank holiday in the place in which any relevant act is to be or may be done; or
(c) a day in the period from 22 December in a particular year to 10 January in the following year, both days inclusive.