• Specific Year
    Any

PETROLEUM AND GAS (PRODUCTION AND SAFETY) ACT 2004 - SECT 820 Internal review decision

PETROLEUM AND GAS (PRODUCTION AND SAFETY) ACT 2004 - SECT 820

Internal review decision

820 Internal review decision

(1) The reviewer must, within 20 business days after the internal review application is made (the
"required period" )—
(a) review the original decision; and
(b) make a decision (the
"internal review decision" ) to—
(i) confirm the original decision; or
(ii) amend the original decision; or
(iii) substitute another decision for the original decision.
(2) If the reviewer does not make the internal review decision within the required period, the reviewer is taken to have made that decision and to have decided to confirm the original decision.
(3) If the internal review decision confirms the original decision, for the purpose of an external review, the original decision is taken to be the internal review decision.
(4) If the internal review decision amends the original decision, for the purpose of an external review, the original decision as amended is taken to be the internal review decision.