412A Provisions about grant and conditions of licence for coordinated project

(1) This section applies if a pipeline licence or proposed pipeline licence is for a coordinated project.
(2) The Minister must not grant the licence until the Minister has been given the Coordinator-General’s report for the project.
(3) Any Coordinator-General’s conditions for the licence must be stated in the licence.
(4) Any other condition of the licence stated under section 412 must not be inconsistent with the Coordinator-General’s conditions.
(5) If a mandatory condition for pipeline licences conflicts with any of the Coordinator-General’s conditions, the Coordinator-General’s condition prevails to the extent of the inconsistency.