• Specific Year
    Any

PETROLEUM AND GAS (PRODUCTION AND SAFETY) ACT 2004 - SECT 392AI Application of div 4

PETROLEUM AND GAS (PRODUCTION AND SAFETY) ACT 2004 - SECT 392AI

Application of div 4

392AI Application of div 4

(1) This division applies if—
(a) the overlapping tenure is a geothermal permit or GHG permit (the
"overlapping permit" ); and
(b) the overlapping permit holder has lodged holder submissions within 4 months after the holder was given a copy of the application; and
(c) the submissions state that the holder wishes overlapping authority priority.
(2) However, this division does not apply if, under the Geothermal Act , chapter 5 or the GHG storage Act , chapter 4 , overlapping authority priority has been given for any of the relevant land.
Note—
If this division does not apply, the petroleum lease application proceeds immediately to decision under chapter 2 as affected by division 7 .