PLANNING ACT 2016 - SECT 72 When development may start

PLANNING ACT 2016 - SECT 72

When development may start

72 When development may start

(1) Development under a development approval may start when—
(a) all development permits for the development have started to have effect; and
(b) all development conditions of the permits that are required to be complied with before development starts have been complied with.
(2) However, if an appeal is started in relation to a development approval, other than an appeal about a change application or extension application, development must not start until—
(a) the appeal ends; or
(b) the tribunal or court hearing the appeal allows all or part of the development to start, because the tribunal or court considers the outcome of the appeal would not be affected.